TIME IS NOT ON OUR SIDE

                            by Alan Benjamin
                     President of Benjamin West

With all due respect to the Rolling Stones classic         they bring to the table? When one thinks of purchasing
1964 hit, “Time is on my side,” for those of us in the     power, it is traditionally in regards to cost. And while
hospitality FF&E world in 2015 and for the near future,    cost is key as we have outlined, today, getting your
time is anything but on our side.                          order to the head of the line and then getting accurate
                                                           and up to the date production and shipping information
Two years ago, my Q1 2012 column was titled “The           is critical.
Year of the Renovation” and I discussed how the
industry was moving past the “Great Recession”             The purchasing agent’s relationship with those vendors
of 2008 and how CapEx was picking up. Well, with           has to be one of mutual respect and trust, and owners
20/20 hindsight, that was not only an accurate forecast    must be open to the information their purchasing agent
but an understated one. If 2012 started us off in “1st     is telling them. I recently had to explain to an owner who
gear” back to where the industry was at its peak in        hired us for two of the same select service brand hotels
2006-2007, then barring any major black swan event,        in the same scheme, about 90 days apart, why we had
the next 3 years, 2015-16-17, should create a new          to change vendors for guestroom carpet, upholstery
record for FF&E spending, throughout all segments          and casegoods from the first to second project. The
of our industry. From catching up on deferred CapEx,       vendors for all three performed fine in the first project,
to scheduled 6/12/18 year cycle renovations, to new        but at the time we went to market for the second project,
construction and a plethora of new brand introductions,    just 90 days later, those vendors’ lead times had shifted
the planets have aligned to create unprecedented           to the point that they were not going to be able to make
global FF&E demand.                                        the required delivery date. One of the major benefits of
                                                           using a large, well-established purchasing firm is that
Given the massive surge in demand for FF&E in our          you get a team that is focused on handling your project
industry, I want to focus on the aspect of time. As        but is part of a much larger firm where all the project
always, in the world of design and construction, almost    teams are in constant communication with each other.
any decision is examined in its relationship to schedule   It is not just that “Vendor A” is now running late on
and budget, the dual dictators of every project, time      casegoods, no, our information is much more micro
and money. While budget is, and always will be, a          and much more current than that; rather, it is what
serious consideration (no one ever hires a purchasing      specific factory from what specific vendor is running
firm to pay more…), let’s examine what stakeholders         what lead time.
can do to maximize their FF&E investment goals in
regards to time in today’s environment.                    Another major factor to consider in the FF&E design
                                                           and construction cycle is what has happened on the
With the frothy mix of events causing unprecedented        project before the vendor receives an order; the time
FF&E demand, the first issue is that almost all the         between when the ID firm is hired and the POs are
owners, brands, designers and purchasing agents            placed. The purchasing agent is only as good as the
want to use the same general list of FF&E vendors.         information above us in the process, so please, as we
While we are always evaluating new vendors, and            have stressed many times, select a design firm that
today purchase from over 2,000 different vendors,          not only has beautiful photos and can produce the
there are industry leading vendors in each FF&E            aesthetic your project demands, but the design firm
commodity that are well established firms with good         that can produce clear, accurate and biddable specs
reputations for delivering the attributes we all want:     on time and within the budget. With the expanding
exceedingly competitive prices, great quality, and         market, many ID firms are looking hard for new staff,
overall, historically good lead times. When hiring a       and it is great to see many of them headed back to
purchasing agent for your project, in addition to all the  their firm’s 2006-2007 levels. But pick the ID firm that
critical budgeting, sourcing, expediting and accounting    has the mentoring and training process in place, as
functions, one of the most important factors an owner      well as the critical double check before the specs go
can consider is how good are the vendor relationships      out the door.
that a purchasing agent has and what kind of power can