Crusader advances gold strategy
Brazil-focused Crusader Resources Paul Stephen Gold exploration and development will
Ltd could pour first gold from its flag- dominate Crusader’s plans for the rest
ship Juruena project before the end of this project after we get Juruena into of this year and into 2017, as the com-
2017. production,†Crusader executive director pany looks to take advantage of rising
Paul Stephen said. precious metal prices and a depreciating
Despite only landing in the company’s Brazilian real.
portfolio two years ago, Juruena is the “Juruena represents an opportunity to
most advanced of Crusader’s develop- move very quickly and could possibly see Borborema, in the north-east of the
ment projects and a second major drill- production within the next 18 months, but country, is set for a second chance at
ing campaign was ongoing at the time of Nova Astro is a much larger prize and life after being put on the backburner fol-
print. something that will require a bigger and lowing the acquisition of Juruena. The
more exciting exploration programme, to company is completing a scoping-level
The 6,000m programme is looking to be hopefully funded out of the cash flow study on a smaller 2 mtpa operation to
increase the size of the overall resource from Juruena. mine the upper lens of the 42mt @ 1.2 g/t
(1.3mt @ 5.6 g/t gold for 234,000oz) as gold reserve.
well as convert some of the inferred re- “This [belt] is highly likely, we think, to
sources at the Querosene and Dona Ma- host more than one major gold deposit. “It’s an asset we believe is going to
ria deposits to indicated status. We’re talking about a cluster of projects come back to the market’s attention,â€
over 8-9km.†Stephen said.
A scoping study will follow a resource
upgrade announcement over the coming “We’ve done a series of optimisations,
months. really focusing in on lowering the strip ra-
tio because the biggest single cost to this
Juruena sits on the north-western tip of project is material movements.
the 400km long, 6 moz Alta Floresta gold
belt, Central Brazil, and was acquired by “If we see a run on the gold price, this
Crusader from TSXV-listed Lago Dour- is really a lottery ticket that is going to
ado Inc in July 2014 for just $C650,000 continue to appreciate.â€
plus shares.
Stephen said he expected the Posse
Crusader also picked up the highly iron ore mine, about 35km from Belo
prospective Novo Astro artisanal mining Horizonte, would continue to remain prof-
centre as part of the transaction. itable for at least the next three years.
“It’s where we see the real upside for – Michael Washbourne
Gold to flow from Cascavel
First gold will be poured at Orinoco thing to take away is that hit a bonanza every 10 or 15
Gold Ltd’s Cascavel project in Brazil underground mine develop-
later this month. ment has been continuing holes,†Spencer said.
unabated and now we have
In the lead-up to Latin America Down more than three months of “We would have to drill on
Under, the final pieces of equipment for stoping ore set up under-
the gravity circuit arrived on site after the ground, ready to bring to a couple of metre spacing
containers carrying the critical compo- surface and put through the
nents were finally cleared through cus- plant.†and spend tens of millions
toms.
First gold from Cascavel of dollars to get this thing
The delay meant the proposed start of will cap a remarkable tran-
production at Cascavel was pushed back sition from explorer to pro- towards a resource, or even
on more than one occasion, but Orinoco ducer for Orinoco since listing in 2012.
chief financial officer Tim Spencer said a reserve. It makes more
the company could quickly make up for Spearheaded by managing direc-
lost time. tor Mark Papendieck and Brazilian co- sense to spend that money
founders Klaus Petersen and Marcelo de
“Once we turn the plant on, we’ll start Carvalho, the company has built up an Tim Spencer developing and collating all
commissioning in late June and then impressive land package along the Faina the knowledge you get from
we’ll put low-grade commissioning ore to greenstone belt and will enter production
settle the plant down and then we’ll be without a JORC-compliant resource for underground development
testing it with some higher grade ore, just Cascavel.
to see what sort of recoveries and rec- to show this can work.â€
onciliations we can take back,†Spencer “It’s a very difficult project to drill in the
said. sense you’re dealing with coarse gold, so Orinoco will initially process 40,000
it’s not homogenous through the deposit,
“We would have loved to have been which means you might drill some holes tpa at Cascavel, but throughput should
producing gold by now, but that has that have very low grades, then you might
been delayed until July. The important double as production levels increase and
more ounces are added to the mining in-
ventory through regional exploration.
Spencer said the company’s Septem-
ber quarterly report would “make for
some very good reading†as it would con-
tain the first actual production numbers
and costings from the project.
– Michael Washbourne