Gryphon goes underground
Gryphon Minerals Ltd has identified Gryphon is targeting an underground resource of up to 1 moz gold at Banfora
a potential underground mining op-
portunity at its Banfora gold project in The result was an upscaled scoping running has always been the key thing for
Burkina Faso. study focused on the simultaneous build us and once that’s sorted and finalised,
of a 2 mtpa heap leach facility and a 1 then obviously we’re off to the races.
And managing director Steve Parsons mtpa CIL plant. Based on a $US1,250/
told Paydirt he was confident of secur- oz gold price, the study found the project “We have a mining permit in place and
ing vital project development funds within could produce 133,000 ozpa over an ini- we’re ready to go on the build, it’s just
the next few months. tial seven-year mine life for $US130 mil- about making sure we have an appropri-
lion in capital costs. ate funding solution. With the gold price
Gryphon reported last month that a re- back up around $US1,200/oz or more,
cent geological and engineering review “Once we’re down through the open pit that makes it much easier for us to get
of the project had demonstrated potential and into where the higher grade material the project off the ground.â€
for a future underground mining opera- sits at the bottom of the pit, we’ll be look-
tion below the proposed Nogbele North ing to try and get into an underground Parsons was also confident the new
open pit. scenario and taking that production up Kaboré Government had brought some
closer to 200,000 ozpa,†Parsons said. much-needed political stability to Burki-
Drilling to prove up a high-grade un- na Faso after a period of uncertainty
derground resource at Banfora was due “It’s very high-level study work at the following the end of Blaise Compaoré’s
to start at the time of print. An explora- moment and we plan to get some holes reign in late 2014.
tion target of 3.5-4.5mt @ 5-7 g/t gold drilled into it in the coming weeks to show
for 560,000oz-1 moz has been set for an that it is robust and then we’ll update the “The new party is in power and life
area down to a vertical depth of 400m study work accordingly.†is back to normal,†Parsons said. “This
below the current open pit design. didn’t really affect anything that was go-
In other good news for Gryphon, pro- ing on in the mining industry, but it made
Last year’s drilling at Nogbele North ject funding appears imminent. Parsons it difficult for mining investment in the
returned a number of high-grade inter- said his company was in the final stages country until things were sorted out.
cepts, including 2m @ 148.62 g/t gold of negotiations with a number of banks
from 35m (including 1m @ 296.4 g/t), 3m and alternative financiers. “However, in the last two months we’ve
@ 120.53 g/t gold from 61m (including seen an enormous amount of capital
1m @ 358.01 g/t), 4m @ 152.65 g/t gold Gryphon has a financing mandate of suddenly going into mining in Burkina
from 19m (including 1m @ 569.01 g/t), up to $US60 million with Macquarie Bank Faso…so I think this year should be a
10m @ 14.74 g/t gold from 29m and 8m and a healthy cash position of $14.4 mil- pretty exciting year for the country.â€
@ 10.85 g/t gold from 132m. lion.
Parsons pointed to Endeavour Mining
“We identified some very high-grade “Things last year with the gold price Corp’s recent $US250 million takeover
material when we were undertaking our the way it was made it difficult for us to of True Gold Inc as well as the former’s
grade control drilling for the banks,†Par- get a funding solution in place that wasn’t $US350 million build of the Houndé pro-
sons said. going to cost us a fortune,†Parsons said. ject as key milestones for Burkina Faso’s
“Now things are much better and I’m hop- mining industry – and ones that are vi-
“We then went and spoke to a mining ing over the next few weeks we’ll have tal to Gryphon’s chances of developing
engineering group that has done a lot of some good news to release to investors. Banfora.
work up in West Africa on underground
mining and we showed them our re- “Finding the full funding solution to get – Michael Washbourne
source and got them to put in what the our Stage 1 heap leach project up and
latest mining costs are for underground
mining in West Africa.
“That report came back looking very,
very positive and basically confirmed that
yes, this is underground material, without
a doubt, and would make money…so our
game plan now is to look at the under-
ground coming on board as a Stage 3
approach to our production scenario.â€
This is not the first time Gryphon has
considered an underground mining sce-
nario, however, the company has always
held the view it would be uneconomic
to target the deeper material until it had
drilled through at least 50m of the depos-
it’s oxide cap.
Gryphon released a robust BFS for the
3.6 moz Banfora project in August 2014,
but a dwindling gold price at the time
prompted the company to go back to the
drawing board and assess other devel-
opment options.
PAGE 14 MAY 2016 AUSTRALIA’S PAYDIRT