                                            Calculate the duration, in days, of the project
                                            of upgrading the sports complex based on the
                                            information on the left.
             SOCIAL WELFARE PROJECT

             PROJECT       : UPGRADING       1December 2019 to 19 January 2021 =               days
                             SPORTS
                             COMPLEX
             STARTING DATE : 1 DECEMBER 2019  1.12.2019 to 31.12.2019 =  31 days
             COMPLETION      : 19 JANUARY 2021
             DATE                            1.1.2020 to 31.12.2020  =  366 days
                                             1.1.2021 to 19.1.2021    =(19 – 1 + 1) days

                                                                                   =  19 days
                                             Total days: 31 days + 366 days + 19 days

                                                          = 416 days

                  1 December 2019 to 19 January 2021 =  416  days

                  The duration of the project of upgrading the sports complex
                  is 416 days.

                              Try to calculate the duration, in days, from 13 June 2021 to
                                                     20 April 2023.







                   1  Calculate the following duration. State the answers in days and hours.
                            :
                                                       :
                        a  9 20 a.m., Saturday to 11 20 a.m., Sunday.
                        b  1650 hours, Monday to 0550 hours, Friday.
                   2  What is the following duration in days?

                        a  2 January 2018 to 13 January 2018.
                        b  14 February 2020 to 6 April 2020.

                        c  9 October 2019 to 5 February 2020.

                   3   Based on the table, calculate the         Shophouses Construction Project
                                                                              Starting  Completion
                      duration, in days, for the:                Project        date         date
                       a  first phase project.                  First phase  22.10.2018   17.1.2020
                       b  second phase project.               Second phase    25.2.2021    3.2.2023