Page 134 - SK Year 5 Mathematics DLP
P. 134
Years, months, and days
Calculate the duration, in days, of the project
of upgrading the sports complex based on the
information on the left.
SOCIAL WELFARE PROJECT
PROJECT : UPGRADING 1December 2019 to 19 January 2021 = days
SPORTS
COMPLEX
STARTING DATE : 1 DECEMBER 2019 1.12.2019 to 31.12.2019 = 31 days
COMPLETION : 19 JANUARY 2021
DATE 1.1.2020 to 31.12.2020 = 366 days
1.1.2021 to 19.1.2021 =(19 – 1 + 1) days
= 19 days
Total days: 31 days + 366 days + 19 days
= 416 days
1 December 2019 to 19 January 2021 = 416 days
The duration of the project of upgrading the sports complex
is 416 days.
Try to calculate the duration, in days, from 13 June 2021 to
20 April 2023.
1 Calculate the following duration. State the answers in days and hours.
:
:
a 9 20 a.m., Saturday to 11 20 a.m., Sunday.
b 1650 hours, Monday to 0550 hours, Friday.
2 What is the following duration in days?
a 2 January 2018 to 13 January 2018.
b 14 February 2020 to 6 April 2020.
c 9 October 2019 to 5 February 2020.
3 Based on the table, calculate the Shophouses Construction Project
Starting Completion
duration, in days, for the: Project date date
a first phase project. First phase 22.10.2018 17.1.2020
b second phase project. Second phase 25.2.2021 3.2.2023
126
4.1.1