9. IMPLEMENTATION TIME LINES

TASK                         PERSON       DATES            ASSESSMENT
                             RESPONSIBLE                   OF TASK

Review and document          TN           05 October
stakeholder challenges       LK           2016
of the Project               AM & TN      05th October
Sign Royalty Agreements      TN           2016
with Stakeholders
Market Research and                       06 – 15 October
Sourcing out of Potential                 2016
Customers
Sign Off take Agreements                  15 – 20 October
with Potential Customers                  2016
                                          24th October
Project Official Launch ALL               2016

Develop an Operational       TN           25 – 30 October
and Production               TN           2016
Scheduling Plan              LK           15 – 25 October
Source Mining and            LK           2016
Crushing Equipment           LK & TN      01-07
Fence and Equip site with                 November 2016
an Office                    CONTRACTOR
Recruit Personnel            ALL          02 November
including employment of                   2016
the local people
Recruit Service Providers                 26 Oct– 04 Nov
such as Security Firm,                    2016
Professionals with Blasting
Certificates, Electrical                  04 – 14 Nov
Contractors etc                           2016
Mobilise and Establish
Mining and Crushing                       16 November
Equipment on Site                         2016
Commence with Mining
and Processing Activities