9. IMPLEMENTATION TIME LINES
TASK PERSON DATES ASSESSMENT
RESPONSIBLE OF TASK
Review and document TN 05 October
stakeholder challenges LK 2016
of the Project AM & TN 05th October
Sign Royalty Agreements TN 2016
with Stakeholders
Market Research and 06 – 15 October
Sourcing out of Potential 2016
Customers
Sign Off take Agreements 15 – 20 October
with Potential Customers 2016
24th October
Project Official Launch ALL 2016
Develop an Operational TN 25 – 30 October
and Production TN 2016
Scheduling Plan LK 15 – 25 October
Source Mining and LK 2016
Crushing Equipment LK & TN 01-07
Fence and Equip site with November 2016
an Office CONTRACTOR
Recruit Personnel ALL 02 November
including employment of 2016
the local people
Recruit Service Providers 26 Oct– 04 Nov
such as Security Firm, 2016
Professionals with Blasting
Certificates, Electrical 04 – 14 Nov
Contractors etc 2016
Mobilise and Establish
Mining and Crushing 16 November
Equipment on Site 2016
Commence with Mining
and Processing Activities
43