Page 28 - Combat Aircraft (January 2020)
P. 28

TYPE REPORT // BOEING KC-46











































              that certi  cation is likely to take three to   September: ‘When we accepted the   KC-46A
              four years.                    KC-46 with known Cat 1 de  ciencies,
               The KC-46A is not yet able to use its   we did so with the belief that it o  ered
              underwing refueling pods. Boeing is   the fastest route to achieve limited   DELIVERY
              moving forward with getting the wing   operational capability and meet an
              aerial refueling pods (WARPs) certi  ed   urgent war  ghter requirement. Eight   STATUS
              by the Federal Aviation Administration   months have passed since our   rst
              (FAA), though former US Air Force   delivery, and Boeing has not made any   Of the 179 KC-46s in the USAF’s
              Secretary Heather Wilson said this will not   progress on the remote vision system.’  program of record, 67 are currently
              be achieved until June 2020.    Within a month of these deliveries,   on contract. In October, the Air
                                             further problems had emerged, with   Force Life Cycle Management
              Deliveries under way           the discovery of tools and other   Center awarded Boeing a
                                                                              $2.6-billion contract modi  cation
              The   rst two squadron KC-46As for the   loose articles in various locations   that covers the production of 15
              USAF were delivered from Boeing’s   inside completed aircraft. Eight tools   Lot 5 KC-46As, plus spares and
              Everett facility in Washington to   were found in aircraft that had been   other support equipment as well
              McConnell AFB, Kansas, on January   delivered to Boeing’s Military Delivery   as two spare engines and   ve wing
                                                                              aerial refueling pod kits. Boeing
              25, 2019, almost two years later than   Center (MDC) and two more in tankers   had previously received its   rst two
              originally planned. The USAF agreed   delivered to the USAF. The KC-46 is built   production lots, for seven and 12
              to accept the aircraft so pilot and   ‘green’ on the main 767 assembly line at   aircraft, in August 2016. The third   Above: A KC-46A
              boom operator training could begin.   Everett before being transferred to the   lot, for 15 aircraft, was awarded in   Pegasus wearing
              AMC commander Miller explained in   MDC, where the aircraft are completed   January 2017; the fourth lot for 18   test registration
                                                                              aircraft in September 2018.  N464KC connects
                                                                               By October, 23 had been delivered   with an F-15E
                                                                              to four units: the 418th Flight   Strike Eagle
                                                                                                           during trials from
                                                                              Test Squadron at Edwards AFB,   Edwards AFB in
                                                                              California; the 344th Air Refueling   2018. Boeing/
                                                                              Squadron (ARS) of the 22nd Air   John D. Parker
                                                                              Refueling Wing (ARW) at McConnell
                                                                              AFB, Kansas; the 56th ARS (the   Left: Personnel
                                                                              KC-46 training unit) under the 97th   from the 60th
                                                                              ARW at Altus AFB, Oklahoma; and   Aerial Port
                                                                              the Air National Guard’s 133rd ARS,   Squadron prepare
                                                                              which is part of the 157th ARW at   to load cargo
                                                                                                           onto a KC-46A
                                                                              Pease Air National Guard Base, New   at Travis AFB,
                                                                              Hampshire. Delayed deliveries mean   California. USAF/
                                                                              that the USAF will seek to slow   SrA Christian
                                                                              down the retirement of the KC-135.  Conrad

          28  January 2020 // www.Key.Aero