the end of last month. It is one of three op-  ticipating inflation to creep into some of the
                                              tions now being considered after Poseidon   costs previously estimated by GR, as well as
                                              contracted GR Engineering Services Ltd to   a potentially longer time to complete all the
                                              investigate increasing the throughput of the   refurbishment works, but assured investors
                                              concentrator to 2.2 mtpa as well as restart-  it would all be within a reasonable range.
                                              ing the operation immediately at that name-  “We got a quote in December last year
                                              plate capacity.                     of $22 million, but we already know it will
                                                Harold said it was unusual to have multi-  be higher than that,” he said. “We’ve also
                                              ple options on the table.           had a slight change in scope – we’re look-
                                                “Normally you only have one option which   ing at repurposing the 150,000 tpa mill for
                                              is you build the plant and optimise the size of   the regrind mill – so there will be some cost
                                              it for the right mining, whereas we’ve got the   escalation, but that’s the market. We don’t
                                              beauty of being able to start off slow and fill   think it’s going to have too much impact on
                                  Peter Harold
                                              it up,” he said.                    the economics.
                                                “The other luxury we have in going from   “When GR looked at it last time, they said
           PBT was earlier this year awarded a $120   1.1 mtpa to 2.2 mtpa is you’re not talking   six months [to restart operations] but they
          million grant from the Federal Government’s   about a lot of extra capital. With the 1.1   might say it’s going to take longer. Obviously
          Modern Manufacturing Initiative (MMI) to   mtpa, what you’re looking at is refurbishing   getting hold of people and other stuff will be
          build the proposed $420 million pCAM hub.  the SAG mill, the float circuit and two of the   a challenge, but we’re starting to address
           Harold said it was no coincidence the   three filters that are already there, and then   some of these things now. It might be tough
          pCAM hub was set to be built just 50km from   for the 2.2 mtpa it’s the SAG mill and ball mill,   out there today, but next year could be less
          Black Swan.                         more flotation and third concentrate filter.   tough, we’ll find out.”
           “For PBT, clearly it makes sense to locate   “We don’t know what the number is yet,   Meanwhile, Poseidon has signed a bind-
          the  project in  WA, and  given  the  amount   but we’re certainly not talking double the es-  ing heads of agreement with Green Gold
          of  nickel  sulphide  that’s  in  the  vicinity  of   timate for what it is for 1.1 mtpa to go up to   Projects Pte Ltd for the processing of gold
          Kalgoorlie, it absolutely makes sense to put   2.2 mtpa. And the other thing is I reckon a   tailings at Windarra, potentially providing
          it there, I can see why they did that,” he said.   2.2 mtpa plant today would cost you north   the company with cash flow to put back into
           “As a result, it’s going to lower the hurdle   of $250 million to build, with all the associ-  Black Swan.
          for a lot of people to get projects up and run-  ated infrastructure, the roads and the tailings                – Michael Washbourne
          ning.”                              dam and all that stuff. So that’s the benefit
           The long-awaited BFS to restart Black   we have.”
          Swan as a 1.1 mtpa operation was due at   Harold said the Poseidon team was an-














                                                                  We believe in
                                                                  a green energy

                                                                  future.

                                                                  Li  Ni Cu Co










                                                                 IGO Limited is an ASX 100 listed company
                                                                 focused on creating a better planet for future
                                                                 generations by discovering, developing,
                                                                 and delivering products critical to clean energy.
                                                                 We are Making a Difference by safely, sustainably and
                                                                 ethically delivering the products our customers need to
                                                                 advance the global transition to decarbonisation.
                                                                 We are the IGO difference.          IGO.COM.AU