Page 62 - pd306-July22-mag-web_Neat
P. 62

OPERATIONAL REVIEW
       DIGGeRs & DeALeRs PReVIeW                                           MACA.NET.AU








        Once, twice, three times the vanadium


































         combination of the public purse and capi-  ting the mining side right is crucial to realis-  There, the concentrate  is  pelletised and
       A  tal markets have set Australian Vanadium   ing everything else the company wishes to   roasted in a grate kiln, then precipitated with
       Ltd (AVL) on its way to finally fulfilling West-  achieve.               a pregnant leach solution before finally being
       ern Australia’s long-held vanadium dream.  “The world needs high-purity vanadium to   converted  into  vanadium  pentoxide  flakes
        WA’s vanadium sector has flickered with   feed the growing markets in steel and bat-  for packaging and export.
       promise  for  nearly  40  years  without  ever   teries,” Algar said. “How does that material   The switch to Mullewa places AVL just
       reaching fruition. However, with global sup-  come about? First you need to make vana-  25km from the gas pipeline, helping to re-
       ply restricted and new applications in steel   dium on the ground, and we can do that with   duce cash costs associated with power con-
       and batteries being developed, WA vana-  our 25-year project in the Mid West of WA.”  sumption. It will also presents an opportunity
       dium’s time could be now.             While the company may not be a conven-  to sell 900,000 tpa of an iron ore-titanium
        Investors and government agencies be-  tional resources firm, the project largely is.   by-product.
       lieve AVL could be the leading light in that   In April, AVL released a positive BFS for   Having studied the vanadium market for
       movement. The last three months have seen   the Australian vanadium project – 43km   several  years,  Algar  believes  there  is  la-
       the Perth-based junior receive $48 million as   south of Meekatharra, demonstrating its abil-  tent  demand  for  AVL’s  flake  product.  With
       part  of  the  Federal  Government’s  Modern   ity to produce 11,000 tpa of vanadium pen-  only three primary vanadium mines outside
       Manufacturing Facility and raise $27.5 mil-  toxide over a 25-year mine life. Capex was   China, there is also growing demand for a
       lion via a placement and SPP.       estimated at $US435 million with the project   high-purity product  sought after  in military
        The funds have been committed to sup-  NPV set at $833 million.         and other specialty sectors.
       port AVL’s three-pronged development strat-  Algar said that with the grant and capital   “There are three vanadium products; pen-
       egy which will see it build a mine producing   raising in place, AVL would push on with   toxide powder, pentoxide flake and ferrova-
       high-quality concentrate for the steel market,   funding.                nadium but all of them are tied back to the
       a vanadium electrolyte plant capable of sup-  “We have started that process now,” he   pentoxide price with premiums above and
       plying product to growing battery demand   said. “We expect it to be a traditional debt/  below so it is a much flatter variation versus
       and a vanadium storage battery business   equity mix and the next six months are very   the iron ore market,” he said.
       itself, servicing mines and other industrial   much focused on offtake and bank due   “We have already produced a high-purity
       projects.                           diligence. We have HCF  International out   99.6% grade product but the critical minerals
        AVL managing director Vincent Algar has   of London advising on the debt and we are   market – the high-end military sector – re-
       been delighted with the interest shown from   working with Canaccord Genuity on the eq-  lies on four 9s [99.9999% purity] and we are
       markets and governments.            uity raising. The plant is to find a cornerstone   working on that now.”
        “It is a critical time for the company and   investor, either new or existing on the share   And, it is increasingly likely the traditional
       these funds allow us to grow the team and   register, and then work up the balance.”  steel market will not be AVL’s sole focus. For
       push ahead with the final parts – both on   While the mining side of the project is sim-  five years the company has been investigat-
       approvals and the technology – so we can   ple, AVL has adjusted the process design to   ing vanadium use in storage batteries. Its
       reach FID by the end of the year and start   take advantage of nearby infrastructure. Ore   solution has been to play a role in defining,
       construction next year,” Algar told Paydirt.  will be mined, crushed and concentrated at   rather than simply finding, the market.
        While the company’s strategy has three   site  before  being  transported  80km  to  the   “Vanadium has been well-regarded in the
       components, there is little doubt that get-  backend facility 35km from Geraldton Port.  critical minerals space but there is going to

                                                                                                 continues on page 65
       Page 62   JULY 2022    aUSTRaLIa’S PaYDIRT
   57   58   59   60   61   62   63   64   65   66   67