Alta back with big resource
















                                                                                           The hills around the picturesque
                                                                                         Italian town of Oltre Il Colle contain
                                                                                                  at least 530,000t of zinc






            trebling of contained metal has deliv-  exploration upside story more believable,”   part of the DFS process but Harris is al-
         A  ered Alta Zinc Ltd exactly the kind of   he said.                     ready confident the Gorno product will at-
         resource upgrade it needed to launch de-  Gorno is a Mississippi Valley-type (MVT)   tract interest from offtakers.
         velopment studies on its Gorno zinc project   orebody with stratabound, breccia and   “We have undertaken our own concen-
         in Italy.                           limestone-hosted zinc mineralisation.   trate  marketing  study  using  a  zinc-lead
           Alta announced the resource update on   “It is a big system, 8km in strike and now   marketing expert and we know we will have
         July 14. The new resource pushes overall   we know a lot more about the mineralisa-  the cleanest concentrate available globally,”
         tonnes from 3.3mt to 7.8mt and increases   tion we have an opportunity to explore the   he said.
         contained zinc threefold. The new resource   potential beyond the resource,” Harris said.  Despite the obvious enthusiasm for Gor-
         stands at 7.79mt @ 6.8% zinc, 1.8% lead   The  recent  upgrade  was  based  mainly   no concentrate, Alta will refrain from signing
         and 32 g/t silver for 530,000t, 140,000t and   on drilling of the Pian Bracca zone which   agreements for now.
         8.04 moz respectively.              sits above the stratabound horizon of the   “Almost without exception the offtakers
           Alta managing director Geraint Harris   original Zorzone orebody. Harris said 3D   don’t get involved until you have a DFS and
         said even he had been surprised by the   modelling of Pian Bracca and other, un-  are 6-12 months  from production,”  Harris
         size of growth.                     drilled, targets highlighted the potential for   explained. “And, if you can get alternative
           “The resource update exceeded expec-  extensions.                      financing it makes it easier to get the best
         tations; we were wanting 6-6.5mt but to   “We used geophysics prior to drilling Pian   terms on treatment charges. That is our
         end up with 7.8mt is tremendous,” Harris   Bracca and it was very successful so we   strategy; the bigger we make the project,
         told Paydirt. “Alone it gives us the critical   are using it again on targets to the north,”   the more interested the offtakers will be.”
         mass for development, but it can also act   he said. “We are getting a lot of value out of   Patience may bring other rewards. Eu-
         as a springboard to 10mt, which is another   lining up the geophysics with what we are   rope is undergoing a minor revolution with
         level again.”                       seeing in the network of adits and what we   the EU and national governments increas-
           Harris is hopeful the positive resource   know from Pian Bracca.       ingly desperate to identify secure supplies
         update acts as a reset for Alta after it en-  “That knowledge will drive success and   of raw materials. As a potential miner in the
         dured a frustrating two years. The company   give us further credibility. We will put an ex-  middle  of  Europe,  Alta  stands  to  benefit
         fell out of investors’ favour as a result of re-  ploration target out for the entire exploration   from the trend.
         source downgrades and a suspended fea-  licence in the coming months.”     “The way the tide is changing, it becomes
         sibility study, then in early 2020 on-ground   In parallel, Alta will begin to rebuild the   an advantage to have a domestic supply of
         activity was suspended as the Lombardy   development story. Harris said the com-  zinc-lead,” Harris said.
         region where Gorno is located became the   pany  had  been  reconfiguring  the  project   Such is the strength of the EU’s push
         epicentre of Europe’s first wave of COVID.   from the PFS with a view to a more efficient   to find new sources of raw materials, Alta
           “A larger resource was always the miss-  operation. The plant site has been moved   is expanding its exploration footprint. The
         ing piece in the jigsaw,” Harris said. “There   closer to the mine and ongoing work is de-  company has already begun work on its
         was a level of scepticism over the size of   signed to match mine and mill throughput   Punta Corna cobalt-nickel project in north-
         the resource so to go from 3.3mt to 7.8mt   with the new, larger resource.   ern Italy and has also applied for additional
         with three times the amount of zinc is a big   “We are working on a concept study now   copper exploration licences.
         step-change. It is proof that we have a pro-  and will then put out a scoping study which   “The EU is putting finance behind ambi-
         ject here and now we can get on with de-  will show people what we have,” he said.   tions to be a raw materials producer and
         signing everything else around it.”   From there, the company plans to move   that is why our ambition is to be a mid-tier
           “Everything else” could include more   straight into DFS.              base metals producer focused on Italy,”
         zinc. Harris said the exploration drilling had   “We have already done a lot of the rock   Harris said. “It is rare that timing works in
         highlighted the extension opportunities still   mechanics and the mine design and a lot of   mining but the energy transition and Eu-
         inherent at Gorno.                  the met test work,” Harris said. “By the time   rope’s refocus on raw materials means we
           “Not only does the resource make the   we finish the scoping study all the pieces   are in the ideal moment.”
         project viable, it shows we understand the   will be in place for a pathway to DFS.”
         geology so much better, which makes the   Metallurgical test work will inevitably be           – Dominic Piper


                                                                                aUSTRaLIa’S PaYDIRT   SePTeMBeR 2021    Page 49