NEWS




                Pantoro charges




          ahead at Norseman





                                    by Dominic Piper
                                                                                                      Paul Cmrlec

             antoro  Ltd’s  proposed  redevelopment  of  the  Central   butter targets” most easily converted into operations feeding the
          PNorseman  gold  project  is  nothing  new  according  to   central 1 mtpa plant, according to Cmrlec.
          managing director Paul Cmrlec. He believes the company will   “Mainfield is actually the best of the resources and was only
          simply  be  the  latest  in  a  line  of  gold  miners  to  successfully   mined to 200m depth. But it requires a bit more work to get it up
          rejuvenate former Western Mining gold assets.         which we will do in Phase 2.
          “It has been demonstrated on several occasions that there is a   Beyond the existing resources, Pantoro is eyeing up a swag of
          lot of gold left in these old Western Mining assets,” Cmrlec told   untested anomalies on both Lake Cowan and land.
          GMJ. “A lot of these sites had not had modern exploration but
                                                                “There are 30 different anomalies on the lake and also multiple
          once they are tested, more gold is found. Norseman has a lot of
                                                                targets off-lake,” Cmrlec said, pointing to Gold Fields’ on-lake
          similarities to Kambalda, where Gold Fields [Ltd] has turned up
                                                                exploration  success  as  an  indicator  of  Norseman’s  wider
          millions of ounces since taking it on.”
                                                                potential. “The comparison to Kambalda is there. Gold Fields
          Like Kambalda, Norseman was thrown on the Western Mining   has found millions of ounces in that field, including Invincible in
          scrapheap in the early-90s after management chose to move   the sedimentary unit, contrary to received wisdom. Norseman is
          away from gold. Croesus Mining was successful in revitalising   on that same sedimentary unit.”
          the discarded asset but for the last 15 years Norseman has
                                                                In May, Pantoro announced its first new discovery at Norseman
          suffered  from  a  lack  of  funding,  for  both  exploration  and
                                                                when the Panda prospect returned hits of 5m @ 24.84 g/t gold,
          operations.
                                                                9m @ 10.84 g/t, 4m @ 8.26 g/t and 9m @ 2.63 g/t gold.
          “Western Mining did very little exploration from the early-90s
                                                                “It  validates  our  systematic  approach  and  our  dual  strategy,”
          onwards  and  subsequent  owners  were  focused  on  remnant
                                                                Cmrlec said. “Panda is a structural target 250m from the Scotia
          mining and low-grade areas,” Cmrlec said. “We have come in
                                                                resource. We are drilling extensions now because Scotia will be
          with a strategy which is seeing the first systematic exploration in
                                                                an important spoke feeding that central hub and the bigger we
          more than 25 years.”
                                                                can make it the simpler it will be.”
          With existing resources of 35.5mt @ 3.5 g/t for 4.4 moz gold
                                                                A feasibility study is being undertaken in parallel with exploration,
          across  25  deposits,  Pantoro’s  greatest  exploration  task  has
                                                                much  of  which  will  focus  on  refurbishment  of  the  plant  and
          been to remain focused in its ways.
                                                                mining schedules.
          “We have stuck with a disciplined approach,” Cmrlec explained.
                                                                “The plant is in poor condition and we need to replace the vast
          “We identified six areas which we can take rapidly into mining
                                                                majority of it,” Cmrlec said. “However, the site is infrastructure-
          and  then  grow  from  there.  Some  are  the  best  resources  in
                                                                rich with offices and workshops, an operating power station,
          the  package,  some  aren’t,  but  they  are  all  capable  of  being
                                                                roads to every resource, a bore field and a tailings dam.
          production ready. As we finish mining them, we can move into
                                                                “On the mining side, we are starting mine design now which will
          the next areas. Eventually we could have three or four areas
                                                                be all tied together in the feasibility study which we are aiming
          producing 200,000 ozpa. That is the ultimate aim, but we won’t
                                                                to release late in Q3.”
          do that until we have got the resources in front of us.”
                                                                Completion of the feasibility study should take Pantoro close to
          Pantoro’s six priority mining centres have more than 1.3 moz
                                                                satisfying a JV condition which requires it to fund the first $50
          gold in resources. Cmrlec said the plan was to extend and infill
                                                                million of project development costs, of which it has around $20
          mineralisation on each with the aim of building a 500,000oz gold
                                                                million to go.
          mining inventory before mining begins.
                                                                Pantoro is comfortable it has the balance sheet to fund its own
          “It needs a lot of testing and extensional drilling before it is ready
                                                                contribution. Halls Creek has been a consistent performer for
          to open and that’s a big step-change for the project,” he said.
                                                                Pantoro with more than 180,000oz produced from two narrow
          “WMC mined mainly from shafts so it always had a short mine
                                                                vein underground mines – Nicolsons and Wagtail North.
          life and subsequently there was very little growth work. We’ve
          been investing upfront to ensure the resource is there.”  “It has been a fantastic performer and a strong contributor to the
                                                                balance sheet,” Cmrlec said.
          Mining  centres  such  as  Gladstone  (268,000oz),  Scotia
          (413,000oz)  and  OK  Mine  (272,000oz)  are  the  “bread-and-