Kwinana Lithium Hydroxide Refinery



           Train I commissioning in progress







                       First lithium hydroxide successfully

                             produced during August 2021








                Saleable chemical grade product expected

                           during December 2021 Quarter








                       Battery grade product for customer

                 accreditation expected during March 2022

                                                  Quarter








               Ramp up to nameplate capacity expected by

                                          December 2022