Jaguar Project Targeted Development Timeline
Q3/2023 – Formal Decision to Mine
Q4/2022 – Definitive Feasibility Study
Q4/2021 & Q2/2022 – MRE Resource Upgrades
Q3/2021 – Lodge Key Environmental Licence
Q1/2021– MRE Upgrade & Scoping Study Results