SHOEMAKER LEVY PROJECT UPDATE (CONT’D)
Above: Primary crusher / sizer area – first ore Above: Primary crusher / sizer area
Concrete – 6,600m3 Peak Workforce - 225
Steel – 2000t of structural steel and platework
Electrical Cable – 90km of cables and 11km of 33kV Overhead powerline 13
Source: FQM