B11 – First drawbell imminent


      BHP’s first developed block cave




       Leinster B11 is progressing the undercut phase


       •   The undercut and the completion of the draw-points is
           expected to be completed  by the end of calendar year
           2022


       •   Ramp  up will continue in 2023.


       •   First draw-bell  firing imminent


       •   Seismic responses to undercutting  in line with expectations
           and plan


       •   Strong QA/QC on tunnel  development  and ground  support

           installation was a key element  of ground  control measures


       •   Caving when commenced  is expected to break-through
           into the old sub level cave after 2-3 years





                                                                                                                     Mined areas above 11L                 Planned Cave
                                                                                                                     Mined areas below 11                   Planned B11 base


          Chris  Stone, General Manager Northern Operations
          5 October 2021                                                                         8