Page 99 - ANC20-Proceedings-Presentations-Full
P. 99

3. More Early Works




          Cassini


          ● Site clearance for surface infrastructure – ROM, offices, site services


          ● Electrical and other infrastructure services commencing this week

          Northern Operations


          ● Underground services and minor rehab at Otter

          ● Electrical and other infrastructure services










                                                                    Haul Road
                            Offices and Workshop

             Settling Dams
                               Box-cut
                                                                 Waste Dump



                                                    Waste Dump


                          Topsoil dump







                                          Site layout – May 2020                                                               Cassini box-cut – May 2020

                                                                                                                                                                                          13