3. More Early Works
Cassini
● Site clearance for surface infrastructure – ROM, offices, site services
● Electrical and other infrastructure services commencing this week
Northern Operations
● Underground services and minor rehab at Otter
● Electrical and other infrastructure services
Haul Road
Offices and Workshop
Settling Dams
Box-cut
Waste Dump
Waste Dump
Topsoil dump
Site layout – May 2020 Cassini box-cut – May 2020