REGIONAL ROUNDUP                                                                             ASIA

Emerald making Okvau sparkle

Emerald Resources NL has cleared a                         Emerald is seeking to begin construction of Okvau in 2018
     major development hurdle in its quest
to start construction at the Okvau gold        required to develop or operate a mine –       of $US419 million and payback in 2.5
project in Cambodia.                           is expected to follow soon after.             years.

   Cambodia’s Ministry of Environment            The acquisition of the first of the neces-    C1 cash costs and AISC are estimated
last month granted an environmental            sary approvals for Okvau’s development        at $US650/oz and $US731/oz respectively
contract for Okvau, paving the way for         continues a bumper 12 months for Emer-        over the life of mine.
Emerald to complete its application for        ald following its takeover of Renaissance
an industrial mining licence as well as        Minerals in November 2016.                      During 2017, Emerald also expanded
finalise a mineral investment agreement                                                      its Cambodian footprint from 347sq km
ahead of first construction works in 2018.       Emerald released a DFS in May which         to 1,500sq km after entering into agree-
                                               found the project could support a 2 mtpa      ments to farm-in to five exploration li-
   “It’s probably the biggest tick the pro-    operation producing 106,000 ozpa over         cences around Okvau.
ject needed to go forward,” Emerald            an initial life of 7.2 years, based on a
managing director Morgan Hart told Pay-        maiden reserve of 14.3mt @ 2 g/t gold           “Okvau is a very, very robust project
dirt.                                          for 907,000oz.                                with a lot of exploration upside to it,” Hart
                                                                                             said.
   “Obviously we’ve still got the funding        At a gold price of $US1,250/oz, Okvau
that we’re paralleling with the licencing      would generate a post-tax NPV of $US110         “This is Cambodia’s first big scale min-
process and then we’ll be in a position to     million, IRR of 40%, gross revenue of         ing project and I know the Government
seriously start talking about constructing     $952 million, pre-tax operating cash flow     is very keen to see it get away because
the project next year.”                                                                      they want to attract other mining compa-
                                                   Okvau is set to become Cambodia’s first   nies into Cambodia.”
   Emerald’s mandated debt financier                      major commercial mining operation
was also close to completing its due dili-                                                     Hart acknowledged he and other
gence of the project at the time of print.                                                   members of the Emerald team had a
Approval of the indicative terms of the                                                      loyal market following because of their
financing proposal effectively guaran-                                                       history of successful mine development
tees funding for the majority of Okvau’s                                                     stories, including Bonikro (Equigold) and
$US98 million capital requirement.                                                           Duketon (Regis Resources Ltd), with
                                                                                             many expecting them to repeat the trick
   The award of an environmental con-                                                        at Okvau.
tract also ensures the 1.14 moz project
remains at the head of the queue to be-                                                        “There have been a lot of people over
come Cambodia’s first major commercial                                                       the years who have been up to this pro-
mine. Under the terms of the contract,                                                       ject to have look and I think it’s fair to
Emerald has provided surety for rehabili-                                                    say they all leave impressed with the
tation of the project area upon the mine’s                                                   prospectivity of the area and the region,”
closure.                                                                                     Hart said.

   Okvau sits within the Phnom Prich                                                           “We’re not necessarily massive pro-
Wildlife Sanctuary and will need to be                                                       moters of stocks; we just like to do pro-
declassed from its current “conservation                                                     motion with actions rather than words.
zone” to “sustainable use zone” to allow                                                     We like to see licences granted, get the
development works to occur.                                                                  banking done and then construct and op-
                                                                                             erate. We think that’s the best way you
   “Just over 40% of Cambodia is under                                                       can promote a company or a project.”
some kind of environmental restrictions,
but the Government allows projects to                                                                           – Michael Washbourne
be excluded from these zones in envi-
ronmentally sensitive areas if there is a
benefit to the rest of the community,” Hart
said.

   “We’ve completed a full environmental
impact assessment on the project, it’s
gone through mediation status with the
Government and the environmental au-
thorities in Cambodia and we’ve come
down to an agreement where they’re
comfortable they can licence the project
and we can move it forward.”

   An industrial mining licence cover-
ing up to 11.5sq km could be issued to
Emerald as early as December, with the
mineral investment agreement – allow-
ing companies to lock in the terms of a
project for the duration of its life, but not

PAGE 100 DECEMBER 2017 - JANUARY 2018 AUSTRALIA’S PAYDIRT