               Site Feature: Rustenburg Chrome Mine


               The contract at Rustenburg Chrome Mine (RCM) commenced 11 November 2021. The
 Equipment:
               onboarding was completed by 20 December 2021 and the first ore was produced in January
 •  3 Excavators –  2022 as per schedule. The operations of Zizwe include the stripping of topsoil, Drilling and
 production and 2  Blasting of Waste and Chrome Ore, removal of waste and chrome ore, and the sizing of
 excavators sweeping  chrome ore.


 •  6 40T ADT’s
               Other than the usual start-up challenges, this specific terrain also posed geological
 •  4 65T RDT’s  challenges while mining close to the dyke. RCM is located in the Kroondal Area, East of

               Rustenburg and owned by Clover Alloys.
 •  2 Dozers

 •  1 Grader  The orebody  The client relies on Zizwe to provide the expertise for the Opencast operation and the
 consists of:  relationship is built on a mutually beneficial partnership. The focus areas for RCM entails to
 Mg3, Mg2, Mg1,  safely mine 650 kT of ore, at an acceptable profit margin to the shareholders.
 Lg7, Lg6a, Lg6
 and Lg5       The team is filled with energy and knowledge, who can deliver results from any
               circumstance.


               “Management cultivated an open-door policy since the very start of the contract, being a
               fairly new site – it is surely something of note that the team already engage very well with
               management,” testifies Ntombekhaya Nyakatyhai, HR Officer.


 The mine is situated +/- 10km
 East from Kroondal.
                   Through teamwork and working safely, we strive to satisfy our client by delivering on our
 RCM Opencast area to mine is  R  commitments. We also strive to care and respect for our fellow employees and the
 approximately 1.8km long
                                     environment while delivering on our commitment.
 Mining started from the  200 000m3 is
 Eastern side of the Pit and              - Christoff van der Westhuizen, Director
 planned per
 progressed to the West.
 month with 55 000
 The reason for this is to
 establish the void for the client  tonnes of reef.
 A dyke structure is situated on the East  to start the new portals to
 access the new underground
 side of the mine
 mine
 The dyke causes the area in proximity to
 the dyke to be disturbed and results in
 selective  mining  which  is  time
 consuming.