               13.  Which one of the following concerns is not suitable for quantitative
                    measurement during the business impact assessment?

                    A.  Loss of a plant

                    B.  Damage to a vehicle

                    C.  Negative publicity

                    D.  Power outage

               14.  Lighter Than Air Industries expects that it would lose $10 million if
                    a tornado struck its aircraft operations facility. It expects that a

                    tornado might strike the facility once every 100 years. What is the
                    single loss expectancy for this scenario?

                    A.  0.01

                    B.  $10,000,000

                    C.  $100,000

                    D.  0.10

               15.  Referring to the scenario in question 14, what is the annualized loss
                    expectancy?


                    A.  0.01

                    B.  $10,000,000

                    C.  $100,000

                    D.  0.10

               16.  In which business continuity planning task would you actually
                    design procedures and mechanisms to mitigate risks deemed
                    unacceptable by the BCP team?