plan provisions and processes?
A. Physical plant
B. Infrastructure
C. Financial resources
D. People
13. Which one of the following concerns is not suitable for quantitative
measurement during the business impact assessment?
A. Loss of a plant
B. Damage to a vehicle
C. Negative publicity
D. Power outage
14. Lighter Than Air Industries expects that it would lose $10 million if
a tornado struck its aircraft operations facility. It expects that a
tornado might strike the facility once every 100 years. What is the
single loss expectancy for this scenario?
A. 0.01
B. $10,000,000
C. $100,000
D. 0.10
15. Referring to the scenario in question 14, what is the annualized loss
expectancy?
A. 0.01
B. $10,000,000
C. $100,000
D. 0.10
16. In which business continuity planning task would you actually
design procedures and mechanisms to mitigate risks deemed
unacceptable by the BCP team?