         At present, the said case is being considered by
         the Supreme Administrative Court. However, the Company
         has followed the procedures of submitting and applying
         for a construction permit correctly and received a permit
         for the construction of modifications (Aor. 1) and building
         operation (Aor. 6) for Robinson Saraburi Branch from
         government officials who have the authority under the law.
         Therefore, it is an internal matter between the government
         sectors as to what criteria are used in considering
         the approval of the issuance of construction permits to
         the  Company  at  that time,  including  the  problem  of
         interpretation of the provisions of the Town Planning Law
         between government agencies that have direct powers
         and duties with the Central Administrative Court that may
         disagree. The Company believes in the principle of honesty
         in the existence of all construction permits which have
         been reviewed and issued by a government official state.
         Therefore, the Company as a private sector deserves
         the protection of its legitimate expectation.