PERSONNEL REQUIREMENTS


                                            Table 6.2: Space requirements for cafeteria



                     Exercise 1:

                            An industrial facility employs 600 people and they are to eat in three equal 30-
                     min shifts, how much space should be planned for a cafeteria with vending machines,
                     serving lines or a full kitchen?

                     Solution:

                            If 36/1 square tables are to be utilized, Table 4.4 indicates 12 ft  is required for
                                                                                        2
                     each  of the 200 employees to eat per shift. Therefore, a 2400-ft  cafeteria should be
                                                                                   2
                     planned.


                            A serving line may serve 70 employees in the first third of each meal shift. Therefore,
                                              2
                     three serving lines of 300 ft  each should be planned. A total of 3300 ft2 would be required
                     for a food service facility using serving lines. A full kitchen will require 3300 ft2 for cafeteria
                                                                                                        2
                     and serving lines plus (from Table 4.5) 2100 ft  for the kitchen. Therefore, a total of 5400 ft
                                                               2
                     would be required for a full service food service facility. Figure 6.2 shows the example of
                     layout for cafeteria.

















                                            Figure 6.2: Example of layout for cafeteria.