Significant Nonroutine Capital Projects Request
                                               FY 19-20
         Street Improvement Construction


         Project Name:       29th St: Oxford to S.H. 107 Construction
         Estimated Total Cost of Project (All Accounts)          $           1,015,000

         Project Description
         1. Location
         29th Street from Oxford to SH 107
         2. Work to be Performed
         Improvement to 29th Street from Oxford to SH 107.
         Construct 2 lane with a continuous left turn and bike lanes

         3. Reason for Work
         Improve Pavement section of 29th Street
         4. Impact on Operating Budget
         Not Applicable




         Personnel Services  $               -         Other     $               -

         Supplies            $               -         Capital   $               -

         Services            $               -            Total  $               -





         Project Name:       Auburn/Trenton Intersection Improvements

         Estimated Total Cost of Project (All Accounts)          $            545,000


         Project Description

         1. Location
         Auburn to Trenton
         2. Work to be Performed
         Road construction extension from Auburn Ave to Trenton Ave.
         3. Reason for Work
         Roadway connection.
         4. Impact on Operating Budget
         Not Applicable



         Personnel Services  $               -         Other     $                 -

         Supplies            $                -        Capital   $                 -


         Services            $                -           Total  $               -