Page 216 - Budget Book FY2020-2021
P. 216
Significant Nonroutine Capital Projects Request
FY 20-21
Traffic/Drainage Bond
Project Name: Northwest Blueline Regrade
Estimated Total Cost of Project (All Accounts) $ 2,598,416
Project Description
1. Location
Trenton Road to Blueline Ditch
2. Work to be Performed
Excavation / re-grading of an existing drain ditch
3. Reason for Work
To maximize storm water conveyance and storage capacity. Also
provide improve access for maintenance activities.
4. Impact on Operating Budget
Not Applicable
Personnel Services - Other $ -
Supplies $ - Capital $ -
Services $ - Total $ -
Project Name: Northwest Regional Stormwater Detention Facility
Estimated Total Cost of Project (All Accounts) $ 5,082,453
Project Description
1. Location
NE corner of North 29th St. and Oxford Ave.
2. Work to be Performed
Analysis and design of regional stormwater detention
facility.
3. Reason for Work
To serve as drainage basin for Northwest Blueline.
4. Impact on Operating Budget
Not Applicable
Personnel Services $ - Other $ -
Supplies $ - Capital $ -
Services $ - Total $ -
-166-