Significant Nonroutine Capital Projects Request
FY 20-21
Traffic/Drainage Bond
Project Name: Bicentennial Blueline
Estimated Total Cost of Project (All Accounts) $ 5,390,215
Project Description
1. Location
Bicentennial Blue Line, Tamarack Avenue to Harvey
Avenue.
2. Work to be Performed
Storm sewer infrastructure improvements to limited
and undersized existing storm sewer system.
3. Reason for Work
Replacing aging infrastructure due to shallow flooding
during severe storm events.
4. Impact on Operating Budget
Not Applicable
Personnel Services - Other $ -
Supplies $ - Capital $ -
Services $ - Total $ -
Project Name: Northgate Lane Drainage Improvements
$ 1,447,371
Project Description
1. Location
Northgate Ln. from N. 2nd St. to N. 10th St.
2. Work to be Performed
Construction of new storm sewer infrastructure, inlets
/laterals to efficiently intercept surface flows and new
storm sewer trunkline.
3. Reason for Work
Alleviating flooding in the area
4. Impact on Operating Budget
Not Applicable
Personnel Services $ - Other $ -
Supplies $ - Capital $ -
Services $ - Total $ -