Project Name: Runway 14-32 / Taxiway A Safety Improvements
Estimated Total Cost of Project (All Accounts) $ 27,287,566
Project Description
1. Location
2500 South Bicentennial - McAllen International Airport
2. Work to be Performed
Installation of flexible base, asphalt pavement.
3. Reason for Work
Adding to the useful life of existing pavement thus
increasing safety for operations and maintenance.
4. Impact on Operating Budget
Slight
Personnel Services $ - Other $ -
Supplies - Capital -
Services $ 15,000 Total $ 15,000
Project Name: Terminal Boarding Bridge Improvements
Estimated Total Cost of Project (All Accounts) $ 4,245,000
Project Description
1. Location
2500 South Bicentennial - McAllen International Airport
2. Work to be Performed
Replace 4 existing passenger boarding bridges.
3. Reason for Work
To increase efficiency and reliability of wait times for
customer travel experience.
4. Impact on Operating Budget
Negligible
Personnel Services $ - Other $ -
Supplies $ - Capital $ -
Services $ 10,000 Total $ 10,000