Page 39 - Forbes - India (January 2020)
P. 39

BharatmaLa





           While earlier development financial
           institutions funded infrastructure   The Gap Between Awards & Execution of NHAI Projects
           projects, they have now turned
           into commercial banks and are         8000                      Execution  Awards          7397
           suffering from the stresses that      7000               6491
           the banking ecosystem is facing.      6000
             There are other challenges too. It                5058
           is mandatory to acquire 80 percent    5000                                      4344  2562  4337
           of land before a project starts; the   Length in km  4000  3360
           mandated amount of land is 90                2693            2706         3067      2562  3071  3320
           percent in engineering, procurement   3000              2248                  2017              2222
           and construction projects (EPC)       2000        1784             1779  1436  1500
           projects. Environment clearances      1000                     1116
           also pose a hurdle, like with the
           `1,850 crore Char Dhaam project.        0  FY2010 FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 FY2019
             To fund its projects, the NHAI   Source   NHAI, IcrA research
           also needs to complete and operate
           projects so that they are monetised.
           Says Burla, “The progress on      instead of the EPC or HAM models.   they were unable to handle risks as
           monetisation has not been as it   TOT projects have seen the interest   they had aggressively bid for these
           was envisaged. In this context,   of a lot of Indian developers tying   projects based on optimistic traffic
           the recent decision by the Cabinet   up with foreign funds. In the three   projections, leading to overleveraging
           Committee on Economic Affairs     Bharatmala projects auctioned under   of their balance sheets.”
           that authorised NHAI to set up an   the TOT model, where the first and   For any infrastructure funding,
           Infrastructure Investment Trust   the third have been successful, the   the new key source is InvITs, where
           (InvIT), a first from a central public   trend is to tap the financial muscle   investors can purchase units of a   39
           sector enterprise, is a positive.”   of foreign funds and the operational   portfolio of completed infrastructure
             The difficulty in raising funds   capabilities of local developers.  assets. While today we see more
           from completed projects is increasing   The government could also try and   private InvITs than public ones,
           NHAI's reliance on borrowings; these   bundle under the BOT programme   NHAI has the government’s nod to
           have risen by more than 2.4 times   projects where land acquisition and   set up its own. Importantly, NHAI
           in the past two years, from `75,385   environmental clearances are not a big   will have to be conscious of the
           crore as on March 31, 2017 to `1.79   challenge. The trend for BOT projects   asset selection as the InvIT portfolio
           lakh crore as on March 31, 2019. It   have changed, explains Mukherjee.   will drive investor interest.
           is expected to double by FY22.    “When the road development           NHAI will release partial
             Mukherjee says, “Earlier, NHAI   programmes started in the late 1990s   payments to highway builders for
           funded most of its projects through   and early 2000s, many developers   their work, even if they don’t achieve
           the BOT model under public-private-  queued up to bid under BOT. But   a milestone. This will ease the path
           partnerships. Apart from land, it   many of them suffered badly as   for developers as working capital
           didn’t have any other significant                                   advance is aimed at completing
           costs. Of late there has a been steep   Contract Sheet              projects and providing liquidity.
           rise in land costs, leading to higher                                  The government’s fight with debt
           debt.” Officials from the NHAI or the    Engineering, Procurement and   will increase their expectations from
                                             Construction (EPC): Government bears the
           Ministry of Road and Transport did   cost, private contractors do the work   the upcoming Budget, but given the
           not respond to Forbes India queries.                                economic conditions, allocations
           Adds Burla, “Since October 2017, 90    Build-Operate-Transfer (BOT): Developer   might not meet expectations. Thus,
                                             builds and operates for a while before
           to 92 percent of projects have been   transferring ownership to the government  as long as funding is concerned, the
           awarded via either EPC or HAM                                       government will have to look for other
           route (see box). Less than 10 percent    BOT-Toll/Toll-Operate-Transfer:   sources. Mukherjee says, “Project
                                             Construction, maintenance and toll collection
           were awarded through BOT-Toll     done by developer                 selection and structuring are key
           route. As a result, the financial                                   to success. Projects in high-traffic
           burden on the government is high.”    Hybrid-Annuity (hybrid of EPC and   corridors that are awarded with
                                             BOT): Government pays 40% upfront;
             The government needs to award   developer initially pays the rest; later the   better preparedness will have higher
           more projects via the TOT model   government pays semi-annually over 15 years  probability of getting funded.”



                                                                                        january 31, 2020 • forbes india
   34   35   36   37   38   39   40   41   42   43   44