Company Overview
Rapidly advancing two DSO projects to
produc,on in the Solomon Islands
1. KOLOSORI (80% PNM)
• Mining Lease granted in September 2022
• JORC 2012 MRE of 6.02Mt at 1.52% Ni (1.2% Ni cut-off) 1
• Posi4ve Scoping Study
o Produc4on of 1.3Mtpa @ 1.5% Ni
o CAPEX approx. US$20m (1 year payback) and
o Opera4ng margins of approx. US$15-20/tonne.
• Debt financing and off-take with Glencore (US$22m)
• Early contractor involvement with HBS - experienced
PNG mining contractor
2. JEJEVO (80% PNM)
2
• JORC 2012 MRE of 7.82Mt at 1.46% Ni (1.2% Ni cut-off)
• Jejevo project poten4al to be a ‘copy and paste’ of the
Kolosori development
1. ASX Announcement 29 September – Updated Kolosori JORC Resource ASX:PNM 3
2. ASX Announcement 7 October 2021 – Ini4al Jorc (2012) Resource Es4mate at Jejevo