Page 102 - pd306-July22-mag-web_Neat
P. 102

OPERATIONAL REVIEW
       DIGGeRs & DeALeRs PReVIeW                                           MACA.NET.AU







                Potash rebound starts to flourish







































                                                                                 Kalium Lakes appears to be overcoming
          urvivors of the embattled West Australi-  400t of commercially saleable SOP, signal-  its initial processing ramp-up issues
      San potash scene are beginning to dream   ling a potential turning point in its recovery,   and is now on track for steady-state
       of brighter times ahead.            with an 80,000 tpa production rate expected   production at its Beyondie SOP operation
        Potash players seemed on the verge of a   to be reached in the March 2023 quarter and
       brand-new industry in early 2021 with Salt   full capacity 120,000 tpa in the September
       Lake Potash Ltd (SO4) and Kalium Lakes   2024 quarter.                   didn’t know what they didn’t know.
       Ltd flying towards production, but 18 months   “We are very pleased that through recent   “So, in the last six months the company
       on the former is in tatters and the latter is   equipment testing and the production of   has sat back and looked at where our short-
       only just beginning to rebuild its operational   SOP we have been able to validate the over-  comings  are  and  set  about  systematically
       credentials.                        all process chemistry and plant design,” Kali-  building organisational capability to cope
        The  scepticism  surfaced  in  mid-2021   um chief executive Len Jubber said. “We are   with the complexities of the project.”
       as reality began to rub up against SO4   now focused on systematically addressing   Potash experts were brought in from the
       managing director Tony Swierizcuk’s bull-  the remaining bottlenecks in the plant and   US to  aid the  recommissioning  process
       ish rhetoric. Having initially said it would   progressively increasing production. Plant   while Jubber focused on turning the com-
       beat construction schedule targets, the   operations during 2022 will be variable, tak-  pany into a traditional miner.
       company announced in July it would miss   ing into account our need to conduct further   “We have set about building operational
       first-year  production  targets  following  un-  mechanical debottlenecking activities and   control to run the bore fields and evapora-
       derperformance of its processing plant and   build inventory.”           tion ponds in a way which is more akin to the
       evaporation  ponds.  A  failed  $100  million   Jubber was brought into Kalium at the end   way you would run a gold or base metals
       capital raising followed before the company   of 2021 as the company struggled to meet   mine with daily, weekly and monthly produc-
       was placed into administration in November.   production ramp-up targets. A highly experi-  tion reports and operational and production
        Kalium only narrowly survived a similar   enced mine developer, builder and operator,   management controls,” he said.
       fate. The company declared itself Australia’s   Jubber saw his initial task as obvious – make   “The next few months will see us moving
       first  sulphate-of-potash  (SOP)  producer  in   Beyondie more like a traditional mining op-  through the mechanics of testing, then into
       October from its Beyondie project but was   eration.                     steady-state production with incremental in-
       quickly raising $50 million to continue com-  “On the one hand, the company had done   creases to production rates out to our stated
       missioning activity as lower-than-expected   remarkably well in bringing a project all the   targets for 2023 and beyond. That will be
       potassium salt feed grades hampered the   way through full construction in a new in-  achieved from increasing harvesting of salts
       ramp-up of the processing plant.    dustry with things that had not been done   from the ponds, improving our organisation-
        Issues continued through the December   before,” Jubber explained to  Paydirt. “But   al capability and debottlenecking the plant.”
       and March quarters but on May 31, Kalium   it was the operational readiness and expe-  In parallel, Jubber is intent on communi-
       announced the successful validation of the   rience which was not there when the com-  cating the Kalium story more effectively, but
       process design had led to the production of   pany was confronted with challenges, they   it is far from a shallow marketing push.


       Page 102   JULY 2022    aUSTRaLIa’S PaYDIRT
   97   98   99   100   101   102   103   104   105   106   107