into the project over the past five years had   posed that the 3,500 tpd plant will convert   remains another key item on the company’s
         gone into ensuring there was minimal or no   sulphur into commercial-grade sulphuric   agenda for the year ahead. Goldman Sachs
         risk to the environment.            acid used to leach lithium and boron from the   is continuing to advise on the various debt
           “The environmental baseline studies were   crushed rock.               options, while the company has signed just
         completed a long time ago – a year and a half   The heat released from this process will be   one lithium offtake agreement to date – with
         ago now – so we’re very aware of any sensi-  recovered to produce zero-carbon steam for   EcoPro Innovation Co Ltd for up to 7,000 tpa
         tive matters on the project,” he said.  electricity sufficient to power the entire Rhyo-  of lithium carbonate over a three-year term –
           “Obviously the Tiehm’s buckwheat is the   lite Ridge operation, as well as the evapora-  representing 34% of the total lithium produc-
         main one, but we’ve had a very good strat-  tion and crystallisation processes required to   tion across the first three years of operation.
         egy around how to manage that, how the two   produce lithium carbonate and boric acid.  While  ioneer  was  quickly  able  to  find
         can co-exist, minimising impact and mitigat-  Veolia was awarded the major supply and   homes for its boron, Calaway said the deci-
         ing for any impact that we do have [is] a lot of   engineering contract, which represents the   sion to hold fire on the lithium, especially with
         scientific research that supports what we’re   single largest supplier package for the con-  prices significantly depressed this time last
         proposing there.”                   tract to date. The group has already started   year, had proved to be correct.
           As part of the $US490 million investment   work on final detailed engineering design of   “We had a lot of ongoing, long conversa-
         agreement, only the South Basin aspect of   the equipment package, with the supply con-  tions but we weren’t prepared to negotiate
         Rhyolite Ridge has been included in the JV.   ditional on a final investment decision.  significant offtake agreements in a bad en-
         Sibanye-Stillwater has an option over 50%   DuPont’s contract is also conditional on   vironment, and I think that paid off well,” he
         of the North Basin (which was not included   FID. Rowe said this had been a deliberate   said.
         in the DFS) for an additional $US50 million,   move by the company to ensure the project   “Our issue at this point, quite frankly, is not
         subject to certain terms and conditions.  was in a shovel-ready position when the final   can we put all our material away in an offtake,
           The ioneer deal was Sibanye-Stillwater’s   permit was awarded.         the real issue is we’re wanting to make sure
         second lithium transaction this year – it had                            the people we’re putting it to are outstand-
         already reached agreement for a 27% stake                                ing offtake partners and whether they are
         in Finnish company Keliber Oy – and its third                            focused on the development of capacity in
         in the wider battery minerals space.                                     the US. Right now, the US doesn’t have sig-
           Sibanye-Stillwater chief executive Neale                               nificant cathode or battery material-making
         Froneman said such transactions were es-                                 facilities, but what we’re focusing on is do-
         sential to the company’s transition towards                              ing deals with companies that have these
         “cleaner green metals” despite still being the                           strong-intent plans to do that so that we can
         world’s largest platinum and palladium pro-                              transition our materials into the US more.
         ducer.                                                                     “There’s a real sense of a potential short-
           “We are excited to build a long-term re-                               age looming and one of the things that’s so
         lationship with ioneer, who share our vision                             important about our project and the potential
         of facilitating security of lithium supply to the                        economics of it is we have a chance at being
         North American markets,” he said. “Rhyolite                              one of the early, new, big pieces of produc-
         Ridge is a world-class lithium project and we                            tion that come on – and certainly will be the
         recognise its strategic value, with the poten-                           first one to come on in the US. That’s an envi-
         tial to become the largest lithium mine in the                           able position and I think people are beginning
         US. We look forward to working collabora-                                to wake up and realise that’s the case.”
         tively with the ioneer team and leveraging our            Bernard Rowe     Rowe believes the company will also be
         complementary skills and capabilities to en-                             pushing the button on Rhyolite Ridge at the
         sure this strategically important, world-class                           ideal time, not just in line with forecasts for
         project is delivered and materially contributes   “If you waited until FID and then went and   lithium demand but with the world starting to
         to reducing climate change.”        said to them, ‘OK, we’ve made FID, now   return to a form of post-pandemic normality.
           Bringing  Sibanye-Stillwater  into  the  fold   we’re going to sign a contract’, they will come   “I think we’re fortunate that we aren’t going
         marked the end of an 18-month global   back and say, ‘well, we’ve got 3-6 months of   out  and  actually  commencing  construction
         search for a strategic partner for Rhyolite   detailed engineering to do before we actually   right now. It’s going to be a much better time
         Ridge following completion of a robust DFS   go on to the site and start building anything’.   to do so in the second half of next year be-
         which forecast production of 20,600 tpa   Here, we’re going to have all of that done in   cause by then everything will be completely
         lithium carbonate and 22,000 tpa battery-  advance,” Rowe told Paydirt.   opened up again, including international trav-
         grade lithium hydroxide (from the fourth year   “Very fortunately, we’re well funded so   el,” Rowe said.
         of operation) for an estimated lowest-quartile   we’re in a position to be able to do that. We   “We’ve done a lot of work over the last few
         AISC of $US2,510/t.                 are spending money – serious money – do-  years  on  where  we’re  going  to  get  labour
           Having  raised  $80  million  via  a  heavily   ing this detailed engineering. It’s in the order   from, how we are going to attract them to the
         oversubscribed placement earlier this year,   of somewhere between $20 and $40 million   area, where are they going to live, all of these
         ioneer has already started a number of pre-  of work over the next 12 months before that   things. I often say to people to have a look at
         paratory works to ensure Rhyolite Ridge   FID decision is made.”         our engineering model and all the test work,
         maintains its status as the most advanced   Danish firm FLSmidth has also been con-  our feasibility [study] and you’ll see an incred-
         lithium project in the US. These include the   tracted to supply the majority of crushing and   ible amount of detail in the work that’s been
         award of major contracts to the likes of Du-  material handling equipment, plus the rotary   done.
         Pont Clean Technologies and Veolia Water   lithium carbonate and boric acid dryers, while   “I remind people that we approach all the
         Technologies Inc.                   ioneer signed a partnership last year with   other aspects of this project with the same
           DuPont was awarded the contract for the   Caterpillar as the exclusive heavy equipment   level of rigour, which includes execution of
         licence, engineering and supply of propri-  partner for Rhyolite Ridge.  the project.”
         etary equipment for the sulphuric acid plant   Finalising the debt component of the pro-
         and will now work with existing engineering   ject financing package, as well as the remain-             – Michael Washbourne
         partner SNC-Lavelin on the design. It is pro-  ing offtake contracts for the lithium products,