Page 26 - gmj147-Apr-Jun-mag-web-neat
P. 26

AUSTRALIAN GOLD REVIEW




           Norseman gets market backing












               by Dominic Piper



             antoro Ltd has clear sight on
          Pfirst  gold  from  its  Norseman
          project in Western Australia after
          locking in an additional $45 million
          of funding in March.
          Pantoro completed the placement
          to  institutional  investors  in  both
          Australia  and  North  America
          and  will  now  sink  the  funds  into
          development at Norseman where
          first gold is targeted for August.
          Managing  director  Paul  Cmrlec
          said  the  decision  was  based  on
                                                                      The 1 mtpa Norseman processing plant is expected to be
          market uncertainty caused by geopolitics and the need to
                                                                                            commissioned in August
          ensure Pantoro was covered through to production.
          “We could see the potential volatility in the market with the
          Ukraine conflict and it certainly proved the right time because   and they started on the Tuesday. They were literally pouring
          if  we’d  waited  another  week,  it  could’ve  been  a  different   concrete as the tanks were arriving on site.”
          outcome,” Cmrlec told GMJ.                            With  labour  problems  as  rampant  as  Omicron,  Pantoro
          From an internal perspective, the additional cash will ensure   chose  to  stay  local  on  the  mining  contractors,  appointing
          the company is comfortable through to commissioning of the   Hampton  Mining  and  Civil  Services  for  the  open  pit  and
          $89 million project.                                  WestAuz Mining for underground services.
          “We had got to a point where it would be tight by the end   “When  we  were  looking  at  mining  contractors,  a  big  part
          of  construction,  so  we  had  to  make  sure  we  had  enough   of  the  consideration  was  their  ability  to  manage  open  pit
          liquidity, especially with COVID in Western Australia and in   and  underground  mining,”  Cmrlec  said.  “That  is  why  we
          the shortages in labour,” Cmrlec added. “It also ensures we   have gone for two smaller, local contractors because both
          have capacity to invest in growth at Norseman and the PGE   have got tight, long-term crews. The ability to meet labour
          discovery at Halls Creek.                             requirements is much more of a driver than a few years ago
          “The market really dislikes companies raising a little bit and   when it was just about price.”
          then going back for a little bit more a few months later. So,   Norseman  is  projected  to  produce  110,000  ozpa  for  the
          we raised enough to put that question away.”          first seven years of operation from three mines; OK Mine,
          The  capital  raising  is  certainly  no  emergency  funding   Gladstone and Scotia. However, the company is positioning
          with  construction  at  Norseman  adhering  to  budgets  and   itself to deliver a much longer production profile.
          schedules. Cmrlec praised EPC contractor GR Engineering   “Under the original schedule we were due to wind exploration
          Services Ltd for its delivery of the 1 mtpa CIL plant on time   and growth back but the capital raising will allow us to keep
          so far.                                               rolling through the first year of production and we believe
          “Once  we  were  pretty  confident  approvals  were  just  a   we can grow the reserve in the next 12-18 months,” Cmrlec
          few  months  away,  we  got  GR  Engineering  to  start  the   said. “We are taking large inferred areas and putting them
          procurement  process,  not  just  the  long-lead  items  but  all   into  reserve.  Norseman  has  never  seen  that  before.  Our
          construction  requirements,”  Cmrlec  explained.  “GR  are  a   600,000oz  maiden  reserve  is  the  biggest  Norseman  has
          really  impressive  organisation  and  their  ability  to  execute   ever had; previously it had always been drilled to keep just a
          is  second-to-none.  We  received  approvals  on  the  Friday,   few years of mine life.”



                                                         Page 26
   21   22   23   24   25   26   27   28   29   30   31