Odysseus mine – underground development progress
▪ Pre-production Activities:
- First development ore intersected
- Back reaming of Leg 1,630m @ 5.7m D
complete
- Winder house construction well advanced
- Odysseus decline development advanced 3km,
now above the Odysseus orebodies
- Pre-production mine development capex
expenditure profile:
- FY22 – A$160m; FY23 – A$55m
- WSA is fully funded with cash and agreed debt
facilities