Odysseus mine – underground development progress






            ▪     Pre-production Activities:



                  - First development  ore intersected


                  - Back reaming of Leg 1,630m @ 5.7m D
                    complete


                  - Winder house construction well  advanced


                  - Odysseus decline development advanced 3km,

                    now above the Odysseus orebodies


                  - Pre-production mine development capex
                    expenditure profile:


                  - FY22 – A$160m; FY23 – A$55m



                  - WSA is fully funded with cash and agreed debt
                    facilities