Odysseus hoisting shaft leg 1 raise bore breakthrough
▪ Completed length of 630m, 5.7m diam –
no issues
▪ Laser survey completed indicating that
shaft verticality is within the 200mm
tolerance
▪ LIDAR survey commenced (3-D hole)
▪ Leg 2 pilot drilling to commence early
November
▪ Shaft commissioning 2 nd Q CY23