AFRIcA DoWn UnDeR PReVIeW




             production clock starts ticking



                                             for Tietto




           est  Africa’s  next  major  gold  mine   10-year mine life, including 200,000 ozpa   Nameplate throughput will be increased
       Wcould be operational before the end of   in the first year. Capex for development of   to 4 mtpa in the DFS after Tietto was able
       2022 if Tietto Minerals Ltd continues to stay   the 3.5 mtpa operation is estimated at $230   to secure an unused mill for Abujar. Wilcox,
       the course with its aggressive development   million, with payback occurring as quick as   who also built the 4 mtpa Bissa and 8 mtpa
       plan for the Abujar project in Cote d’Ivoire.  2.4 years after first gold.  Bouly operations, described the purchase
         Tietto has set an ambitious target of   The PFS was  based on  a reserve of   as “quite a boon” and said it would amount
       pouring  first  gold  from  Abujar  within  the   15.7mt @ 1.7 g/t gold for 860,000oz, but Ti-  to higher processing capability for a much
       next  18  months  despite  still  being  in  the   etto is preparing for a “material” increase to   lower cost.
       pre-development phase. Tenders are out   that estimate in the upcoming DFS after last   “The mill is the heart of the process plant.
       for early site works and other construction-  month upgrading the resource to 87.5mt @   If you get the mill right and you size the mill
       related activities, while a DFS is due at the   1.2 g/t gold for 3.35 moz, of which more   right, you will never have a problem with the
       end of next month.                  than 55% is now classified as indicated.  amount you need to process,” he said.
         The development timeline might appear   “It was really pleasing to see an almost   “No one ever blames you when a mill is
       too tight for some, but Tietto managing di-  50%  jump  in  the  indicated  resource  cat-  bigger than it needs to be. It’s much hard-
       rector Caigen Wang has full confidence in   egory, which was the focus of our drilling,”   er and more expensive to expand a plant
       his team to deliver the project according to   Wang said. “We also had an 11% growth   down the track so if you can build in that
       script. In fact, he believes his company is al-  in the quantity overall, which is also pleas-  extra capacity early it makes it a whole lot
       ready tracking ahead of schedule in certain   ing because we were not aiming for any re-  easier. I’ve done that with every plant I’ve
       areas of the process.               source growth.                       built  because  you’re  always  trying  to  in-
         Speaking to Paydirt last month after an-  “We are now expecting a much bigger   crease the throughput. WAF achieved that
       nouncing a resource upgrade for Abujar,   uplift in the reserve compared to what we   higher throughput and I think we’ll be able to
       Wang pointed to a number of the compa-  delivered in the PFS.”           push above nameplate.”
       ny’s past achievements as evidence the                                      With the DFS nearing completion,
       proposed development timeline was no-  Tietto recently upgraded the resource at Abujar   Wang indicated discussions with poten-
       where near as ambitious as some outsid-  to 87.5mt @ 1.2 g/t gold for 3.35 moz, including   tial debt providers would start to ramp up
       ers might think.                     a 49% boost in indicated resources to 43.4mt   over the coming months so Tietto can
         “Normally in our situation people will                @ 1.3 g/t for 1.85 moz  seamlessly move into the mine construc-
       wait until the DFS is completed before                                    tion phase without having to wait for pro-
       progressing on the project development                                    ject financing to be sorted.
       side, but we are achieving well ahead of                                    The rigs will also keep turning at Abu-
       our DFS,” Wang said.                                                      jar with the company looking to complete
         “We completed our processing plant                                      50,000m of diamond drilling before the
       DFS at the end of May to give us a very                                   end of the year. The programme will in-
       good technical background to proceed                                      clude infill drilling at the main AG deposit
       with processing  plant  development                                       targeting the first two years of production
       and other long-term items for the mine                                    and resource growth from drill testing of
       construction. So, we are well ahead of                                    targets within 10km of the mill.
       schedule in that area of project develop-                                   “I’m very happy with the performance
       ment.                                                                     of our drilling team,” Wang said. “The
         “If you look at our track record since                                  six diamond rigs we have on site are
       September 2014 – when we received the                                     averaging between 7,000m and almost
       exploration licence – up until now, in less                               12,000m per month. The performance is
       than seven years we’ve developed from                                     exceeding our expectations.”
       nothing on the tenement to a 3.35 moz                                       Wang said the fact three gold mines
       resource and a DFS coming in Septem-                                      – Sissingue, Yaore and Ity – have been
       ber. I think the speed we’ve had in the                                   switched on in Cote d’Ivoire during the
       past  demonstrates  our  capacity  to  de-                                very recent past was a good sign for Ti-
       liver the project.”                                                       etto as the countdown begins to first gold
         The Abujar build is being led by Tietto                                 from Abujar.
       chief operations officer Matthew Wilcox,                                    “The West African region is definitely
       who was responsible for construction of                                   one of the best gold investment destina-
       three  other  gold  mines  in  West  Africa                               tions in the world and a number of big-
       during the past decade, including West                                    sized gold mines have been built in the
       African Resources Ltd’s 300,000 ozpa                                      last few years,” he said. “That gives us
       Sanbrado mine in Burkina Faso.                                            really good confidence we can follow in
         According to the PFS published in                                       their footsteps to develop another one.”
       April, Abujar is forecast to produce an
       average 168,000 ozpa over the initial                                               – Michael Washbourne