Page 46 - ARCHITECTURE SITE PRACTICE
P. 46

CERTIFICATE OF NON-
                   COMPLETION












                  The  certificate  of  non-completion  gives  formal  written
                  notice  to  the  contractor  that  they  have  failed  to  complete
                  the works described in the contract by the completion date
                  that was last agreed (the original completion date may have
                  been adjusted during the course of the works).

                  The date for completion of construction works (or dates for
                  completion of sections of the works) is generally set out in
                  the  contract  particulars.  However,  it  is  not  uncommon  for
                  delays to cause the completion date to be missed, that is, the
                  works  are  not  complete,  and  so  a  certificate  of  practical
                  completion cannot be issued by the date for completion.

                  Where the client is responsible for the delay, an extension of
                  time may be granted, the completion date adjusted, and the
                  contractor may be entitled to claim loss and expense.


                  Where the contractor is responsible for the delay, the client
                  may be entitled to claim liquidated and ascertained damages
                  (at a rate set out in the contract particulars).












































                                                                                                                  39
   41   42   43   44   45   46   47   48   49   50   51