Page 3 - Under The Roof Avonside Group staff newsletter - June 2019
P. 3

UNDER THE ROOF





            AVONSIDE PROJECTS

            Avonside Midlands Flat Roofing Overcome

            Logistical Challenges



            THE PROBLEM: WATER INGRESS
            Avonside Midlands Flat Roofing were asked to help
            client Wilkinson Environmental find a cost-effective
            and viable solution for Biffa’s High Wycombe waste
            recycling office’s leaky roof. The building suffered from
            water ingress as a result of the existing EPDM
            (Ethylene Propylene Diene Monomer) system having
            failed. Computers were kept on the top floor of the
            office building, so it was vital that the issue was solved
            promptly and efficiently.
            THE SOLUTION
            After Avonside Midlands carried out surveys of the site
            to assess the client’s needs, scale of the issue and
            scope of the project, they proposed installation of the
            RENOLIT PVC Single Ply system (total surface area
            700m²) as a viable and cost-effective solution, with a
            20-year warranty that met the client’s requirements.
                With their proposal accepted, the Midlands team
            began installing a 1.5mm-thick light-grey RENOLIT PVC
            Single Ply ALKORPLAN system. The membrane was
            fastened mechanically. While RENOLIT supplied the
            main roofing accessories, the fixings manufacturer was
            Fixfast Ltd, and the other products used in the project   TICK TOCK!
            were by Olympic. The installation was successfully   Due to the site being a functioning office, completing
            completed, headed up by the Project Lead, Matthew   the project to a high standard in the designated
            Savage, who is L2 NVQ single ply qualified.       3-week schedule was imperative so staff could have
                                                              access to car parking spaces again. Avonside Midlands
            LOGISTICAL CHALLENGES                             are proud to say the job was largely completed in 2
            As the Biffa waste recycling building was still a   and a half weeks, ahead of schedule.
            functioning office whilst Avonside Midlands staff
            worked on-site, they had to be considerate and keep   AVONSIDE MIDLANDS MEAN GREEN!
            noise to a minimum. Part of the project involved   The team opted to avoid stripping the original roofing
            drilling, and the noise restrictions meant they couldn’t   system, so the old materials didn’t have to go to the
            drill at certain times. The Midlands team worked   landfill. Instead, they overlaid the new waterproof
            around the office workers, who equally worked around   system and avoided leaving the building exposed to
            the team by sometimes using laptops and working in a   the elements.
            different location.
                Parking was also limited on the site due to it being   SAFETY FIRST!
            in use by office workers. Scaffolding needed to be   Health and safety were big priorities for the team,
            erected, which Wilkinson Environmental collaborated   especially as they were working on a site with offices in
            with Avonside Midlands on, organising the scaffolding   operation. All labourers were fully inducted in terms of
            for the team as well as providing a forklift to get all the   Health and Safety, plus all the relevant risk
            necessary materials up on the roof conveniently and   assessments were carried out. Regular Toolbox talks
            efficiently in one day. The scaffolding did take up some   were had with labourers and all staff, addressing
            car parking spaces, so efficiency was vital.      issues like the safety aspects of working at height.







       www.avonsidegroup.co.uk
   1   2   3   4   5   6   7   8