UNDER THE ROOF





            PLOUGHCROFT PROJECTS
            Back to School for



            Ploughcroft!



































            WHEN THE MAIN ROOF OF EASTWOOD COMMUNITY          APPLYING THE SIKA LIQUID SYSTEM
            SCHOOL IN KEIGHLEY, WEST YORKSHIRE, REACHED       Once the metal surface had been de-rusted, it was
            THE END OF ITS DESIGN LIFE, IT BEGAN TO LEAK IN   degreased using a solvent-based degreaser.
            VARIOUS PLACES.                                   Ploughcroft then thoroughly rinsed it off with fresh
            —                                                 water, applied Sika Liquid Plastics Metal Primer to all
            Luckily, Ploughcroft stepped in and carried out a liquid   prepared exposed metallic surfaces, and allowed it to
            plastic re-roof on the school’s 2000m² profile metal   dry before coating it with Sikalastic 625 Liquid Metal &
            roof, a project that lasted 12 weeks. The bad condition   Asbestos Plastic System.
            of the roof membrane was typical throughout the
            entire roof area, so it was proposed that a Sika Liquid
            System be applied over the roof area to give a 15-year
            guarantee.

            PREPARATION IS KEY!
            Before the initial cleaning of the roof area, the
            Ploughcroft team had to remove all surface debris by
            hand, along with any visible growth and vegetation.
            They also had to protect all outlets to make sure no
            debris entered the drainage system. All rust had to be
            removed by wire brushing, returning the surface to a
            bright, clean metal where possible. The operatives
            tightened any loose fixings (or replaced when
            necessary) and replaced any corroded, damaged or
            missing fixings.