CIVIL ENGINEERING &
                                                                                                                   INFRASTRUCTURE WORKS




                                                                                              Project highlights

                                                                                              •    PMSB was tasked with commencing the
                                                                                                   upgrading works without halting any of

                                                                                                   the dam’s operations. At the same time,
                                                                                                   we were to maintain the cleanliness

                                                                                                   and quality of the water from the dam
                                                                                                   as it supplied raw water to almost 50%

                                                                                                   of the population of Perlis.



                                                                                              •    The upgrading works faced its biggest
                                                                                                   challenge when Perlis was hit by two

                                                                                                   big floods in 2010 and the water level
                                                                                                   was at the danger level for almost a

                                                                                                   month for both events. At the height
                                                                                                   of this crisis, there was an incident

                                                                                                   when the overflow even breached the
                                                                                                   emergency spillway. Nevertheless,

                                                                                                   the  dam  embankment  filling  works
                                                                                                   were completed six months ahead of

                                                                                                   schedule, while rip-rap works finished
                                                                                                   one month ahead of schedule.



                                                                                              •    From a safety perspective, the project

                                                                                                   was nominated to represent the state
                                                                                                   of  Perlis  at the  national-level Safety

                Rip-rap protection to main dam upstream.                                           Best Practice Awards competition.