CIVIL ENGINEERING &
                                                                                                                   INFRASTRUCTURE WORKS

            Project highlights
            •     In constructing the new carriageway, it passed through fringe virgin

                  jungle where at certain locations small streams could turn into fast
                  flowing floodwaters especially during the monsoon season. To protect
                  bridge construction works over the monsoon period, major shoring
                  and sheetpile cofferdams were put in place.



            •     The constant high water level at Sg. Tanum (Segment 5) especially
                  during the monsoon season also prompted the innovative use of
                  sinking caisson walls to accommodate the bridge pile cap construction

                  works that were located below the riverbed level.


            •     In late 2009, strong currents and flooding destroyed the temporary
                  steel bridge built across Sg. Tanum but we were able to restore this

                  immediately. Despite the interruption of the only access across Sg.
                                                                                    The “eco-bridge” at section 3F offers uninterrupted crossings for the wild animals.
                  Tanum during the earthworks stage, earthworks for Section 1 of the
                  project was completed on time due to the effective recovery plan we
                  had in place.



            •     The construction of the  Vehicular Box Culvert (“VBC”) at CH2000
                  necessitated a major traffic diversion that posed a safety hazard due
                  to speeding traffic at the previously straight road section. Due to the

                  exceptionally high traffic safety standards and features provided, no
                  major traffic accidents involving fatalities were recorded at Section 3F.


            •     The overall construction  works at Section 3F were completed six

                  months ahead of time following the introduction of the precast spine
                  beam and slab construction method for eco-bridge works in place of
                  the conventional cast-in-situ method.



            •     Again, the Section 3E2 was completed and delivered ahead of time.
                  This scenic route is adorned by the beautiful limestone formation on   The dual carriageway opens to a smooth flow of traffic.
                  both sides of its dual lane carriageway.