BUILDING
                                                                                                                           CONSTRUCTION



            Project highlights
            •     Construction works had to be undertaken in a very

                  tight working space due to the adjacent buildings
                  and  roads.  Contiguous  bored  piles  were  utilised

                  to protect adjacent buildings in the basement
                  excavation.



            •     Despite strict working hour conditions stipulated

                  by the Kuala Lumpur City Council, the project was
                  successfully completed on time without any major

                  departure from the original schedule.



            •     The project successfully tapped innovative
                  construction technology. One of the main

                  innovations  was the introduction of the state-of-
                  the-art M2 energy saving  wall panels adopted

                  from EMMEDUE® advanced Italian building
                  system technology. The latter utilises sintered foam

                  polystyrene materials (EPS) to replace conventional
                  brick and RC walls.



            •     The project achieved a GBI Gold rating for its high

                  energy efficiency and good indoor environmental
                  quality  elements.  The  implementation  of  a

                  stringent Environmental Management Plan with
                  monthly environmental monitoring for air quality,

                  water  saving  efficiency  and  noise  levels  ensured
                  that construction works were carried out in an

                  environmental friendly manner.


                                                                                                              PESONA METRO SDN BHD 45