                                    Figure 9-2 test being carried out






                      Limit State Design



                      Introduction

                      Traditionally, design resistance of foundations has been evaluated on an
                      allowable stress basis that piles were designed with ultimate axial capacity
                      between 2 and 3 times than working load. However structural design is now
                      using a limit state design (LSD) bases whereby partial factors are applied to
                      various elements of the design according to the reliability with which the
                      parameters are known or can be calculated. LSD approach is the base of all the
                      Eurocodes, including that for foundations design. It is believed that Limit state
                      design has many benefits for the economic design of piling. The eurocode
                      approach is particularly rigorous, and this guide adopts the partial factors
                      presented in the codes.

                      Eurocode 7 divides investigation, design and implementation of
                      geoconstructions into three categories. It is a requirement of the code that project
                      must be supervised at all stages by personnel with geotechnical knowledge.

                      In order to establish minimum requirements for the extent and quality of
                      geotechnical investigation, deign and construction three geotechnical
                      categories defined. These are: Geotechnical Category 2, 2, 3.

                      20.2 Goetechnical category 2, GC 2

                      this category includes small and relative simple structures:

                      -for which is impossible to ensure that the fundamental requirements will be
                      satisfied on the basis of experience and qualitative geotecnical investigation;

                      -with negligible risk for property and life.

                      Geotechnical Category 2 procedures will be only be sufficient in ground conditions
                      which are known from comparable experience to be sufficiently straight-forward