                  2.2  Local or imported projects

                  The project of the KNX installation must be contained in the database for commissioning
                  purposes. If the project has been configured on a different PC, there are two possibilities:

                  The first option is to import the exported project with ETS onto the commissioning PC. The
                  necessary steps are described in the “Project design” chapter. It is however necessary to
                  ensure that all additional installed programs e.g. for touch panels are also installed on the
                  commissioning PC.













































                  Figure 1: Local or imported projects























                  Home and Building Management Systems                                    KNX Association
                  ETS Commissioning                ETS4_Commissioning_E1212b                          4/24