Page 35 - Approved Annual Budget FY 2019-2020_Flat
P. 35
Traffic Management Improvements – Cabinets Replacements
Management’s Response: Traffic Cabinets replaced at various locations completed. Ongoing project,
Operations staff has completed the installation/upgrade of traffic cabinets along the 10th Street and
2nd Street; Staff is in the process of completing cabinet upgrades along the 23rd Street corridor; other
locations will be identified and replaced.
th
29 Street (Oxford to 107)
Management’s Response: Ongoing project, Roadway design and ROW acquisition is complete; Road
closure is being implemented, with Phase III of the roadway underway. Contract completion March
2020.
Improve City Storm Drainage
Regional Storm water improvements –Kennedy Avenue
Management’s Response: This project consists of the installation of approximately 3,630-linear feet of
storm drain pipe along Kennedy Avenue, Jackson Avenue, and Colonel Rowe Boulevard.
Construction to begin in October 2019.
Regional Storm Water Improvements - Westway Heights
Management’s Response: This project consists of the installation of approximately 7,000-linear feet of
storm drain pipe within Westway Heights Subdivision. Construction anticipated to complete in
November 2019.
Regional Storm Water Improvements – Pecan Blvd at N. 27 Street
th
Management’s Response: This project consists of storm sewer infrastructure upgrades to a section of
the existing system on Pecan Boulevard. Completed in August 2019.
Regional Storm Water Improvements – Sarah Avenue
Management’s Response: Roadway paving and drainage improvements to construct a segment of
Sarah Avenue from Ware Road (FM 2220) to west boundary line of IDEA School South McAllen.
Drainage improvements complete as of August 2019, pending final inspection and punch list.
Leisure, Cultural and Entertainment
Bicentennial Hike and Bike
Management’s Response: Extension of Hike and Bike trail along with addition of amenities to
continually encourage use of linear parks. Completed in Fiscal Year 2019.
Trail Enhancements
Management’s Response: Enhancement of trail along Bicentennial/2nd street. Completed in Fiscal
Year 2019.
Municipal Bath house
Management’s Response: Installed new plumbing within bathhouse restrooms and remodel of
showers for ADA accessibility. Completed in Fiscal Year 2019.
Accomplishments of Prior Major Goals xxiv