SECTION 5.0 – ARCHITECTURAL COMPONENTS, MATERIALS AND FINISHES                                                         SECTION 5.0 – ARCHITECTURAL COMPONENTS, MATERIALS AND FINISHES



                                  metal deck or other approved materials shall act as a primary roof covering                                               shall be used for large roof areas to accelerate water discharge under
                                  above the reinforced concrete slab to prevent leakage and water ponding.                                                  BS 6367: Code of Practice for Drainage of Roofs and Paved Areas.

                        5.2.6     Suppose a reinforced concrete flat roof is used. In that case, it shall be                                             g)  Gutter for marine environment shall be pre-painted finish with metallic
                                  provided with high performance and chloride-free material waterproofing                                                   coated steel with minimum aluminium/zinc-alloy as stipulated in the
                                  system, with a bonded warranty for not less than ten (10) years in addition                                               latest  JKR Standards  Specification for Building Works and other
                                  to a general warranty provided by the contractor. The sample of material                                                  guidelines as listed in 5.1.3.
                                  shall be submitted for the PD’s concurrence.

                        5.2.7     The roof used shall be of a complete roofing system consisting of tiles,                                     5.3       FLOORS
                                  fittings, roof system components, and accessories designed to cater for a
                                  variety of  roof finishing details in compliance with the  manufacturer’s                                    5.3.1     Floors shall be concrete slab unless otherwise specified and floor finishes
                                  technical specifications, including minimum recommended pitch of the roof                                              are shown  in  Appendix 3  –  Schedule of Summary of  Architectural
                                  (roof tiles gradient).  The colour of the tiling fillers shall match the colour of                                     Components and Materials. All plastering, paving, and tiling works shall
                                  the roof tiles.                                                                                                        comply with the latest JKR Standard Specification for Building Works.

                        5.2.8     Roof tiles shall conform to MS 297, and unless otherwise specified on the                                    5.3.2     All size, pattern, and colour of floor finish materials shall be of the PD’s
                                  drawings,  they  shall be laid on  the metal  trusses system to engineer’s                                             concurrence with HODT’s and the Client’s verification, if necessary.
                                  details and PD’s approval. The  tiles shall be  free  from all defects and
                                  fungus.                                                                                                      5.3.3     Workstation and  computer rooms shall have anti-static  vinyl floors. The
                                                                                                                                                         raised  floor system (i.e.,  for ICT  rooms), wherever specified, shall have
                        5.2.9     Whenever metal roof decks are used, it shall be a concealed fixing system                                              adequate space underneath for pedestal, wiring, cables with cable outlets,
                                  of a minimum of 0.48 mm thick based metal (BMT) of pre-painted aluminium                                               and electrical openings. The raised  floor system shall be flush with the
                                  and zinc-coated steel on both surfaces.                                                                                surrounding floor finishes.

                        5.2.10    Gutters and Rain Water Down Pipe (RWDP):                                                                     5.3.4     All floor areas requiring sports activities shall be constructed and finished
                                                                                                                                                         with appropriate systems and materials  that meet sports standards.
                                  a)  All  roof drainage  systems  shall  be  completed  with  roof  accessories,                                        Outdoor and indoor sports court shall be finished with sports court surfacing
                                     including gutters, debris strainers, and RWDP  with bracing. RWDP                                                   system (e.g.,  rubber paint, epoxy,  or  PU paint finished) to the PD’s
                                     bracing shall be installed to sustain vibration from the rapid water flow.                                          concurrence.

                                  b)  Placement of gutters and RWDP shall be aesthetically integrated into                                     5.3.5     All  floor  skirtings  shall  be  not less  than  100  mm  high  unless  otherwise
                                     the overall façade design or concealed. Numbers and sizes of RWDP                                                   specified.
                                     shall be determined and endorsed by the Civil Engineer.

                                  c)  Wherever  uPVC  or  zinc-alloy  coating  steel  gutters  and  rainwater                                  5.3.6     Vinyl
                                     downpipes are used, they shall comply with MS 1063, MS 1196 and
                                     shall be provided with a bonded warranty not less than five (5) years.                                              a)  Vinyl sheet or vinyl tile flooring shall be of minimum 2 mm thick high-
                                                                                                                                                            performance premium quality homogenous type (Type T or Grade 1),
                                  d)  Roof gutters shall be of non-corrosive and non-toxic materials, durable,                                              specified following  the  function of  the room or  area, carried out by
                                     able to resist all climatic effects, and remain dimensionally stable over                                              specialists from the approved supplier of the material and complies with
                                     time.  Its profile shall  complement  any  architectural  style,  easy  to                                             manufacturer’s  method of installation,  to the following types and
                                     assemble, lightweight, and maintenance-free.                                                                           performances:

                                  e)  RWDP in reinforced concrete column shall be avoided.                                                                   i.  Vinyl Type 1: Heavy-duty to withstand heavy traffic of trolleys.
                                                                                                                                                             ii.  Vinyl Type 2: Anti-static conductive to cater for aseptic and dust-
                                  f)  RWDP shall be avoided inside the building, and any exposed RWDP at                                                        free  environment (meant  for  OT Room, Server Room, Imaging
                                     the circulation area shall be protected. RWDP with a siphonic system
                                                                                                        26                                                                                                                     27