ReGIonAL RoUnDUp




                 Kingston funded to go town





          study manager will soon be appointed   be the starter  for mining via the Ewati-  2022 was the target. The environmental
       A  to drive the Misima PFS for Kingston   nona pit (recent rock chip sampling re-  approvals process has started, however,
       Resources Ltd in PNG.               sults from outcropping 70m @ 4.99 g/t,   travel restrictions due to the coronavirus
        And, with $8.4 million recently locked   including 28m @ 8.08 g/t  and including   may cause some delays.
       in by the company, whoever takes charge   6m @ 15.58 g/t, 12m @ 3.67 g/t and 4m   Corbett said the virus hadn’t affected
       can proceed with study work without   @ 10.96 g/t).                      PNG in a meaningful way with the Gov-
       funding worries.                      “It is a big project so people should be   ernment handling the situation very well.
        “We are targeting to have the PFS on   looking for a big [maiden] ore reserve and   With Kingston’s senior geologists and
       Misima out at Christmas time and hope-  that is what we think it is going to be. Of   drillers being expats, site work at Mi-
       fully we will get drilling at Misima before   the 3.2 moz resource, we have 1.5 moz   sima is in a holding pattern for now. In
       that  and  also  completing  100%  owner-  in the indicated category, so if everything   the meantime, the company is preparing
       ship of the project in the next six months   goes well and if they get to reserves that   for a tilt at the Livingstone gold project,
       as well,” Kingston managing director An-  is a pretty big number,” Corbett said.  140km north-west of Meekatharra in
       drew Corbett told Paydirt recently.   “We’re looking at a 10-year mine life   Western Australia.
        “We  have an  agreement  to  move  to   and a pretty big project. Placer’s pro-  The  company  owns  75%  of  Living-
       100%  ownership  of  the  project.  It  has   cessing plant was 5 mtpa, we expect to   stone, where the Homestead prospect
       taken us two years to get from 49% to   have a similar size because at 1 g/t gold   contains a 49,000oz gold resource (18m
       100%,  so we have ticked a few boxes   you’d want to have a pretty big process-  @ 7.85 g/t from 68m, 5m @ 20.5 g/t from
       and we’ll just have to wait and see.”  ing plant.                        3m and 7m @ 12.59 g/t from 35m). King-
        Corbett’s later comments were in re-  “We are planning to do what Placer did.   sley is shaping as another likely pros-
       sponse to a question concerning King-  We’ve got their mill designs and process-  pect, with RC drilling last year intersect-
       ston’s rating as a potential takeover tar-  ing plant here, so we are just repricing   ing 10m @ 11.95 g/t from 20m, 5m @
       get given how large a project Misima is   the same plant. We are using the same   3.68 g/t from 12m and 2m @ 13.88 g/t
       shaping as.                         location,  haul  road,  ports  and  airports   from 71m.
        A former Placer Dome asset, Misima   and digging up the same pits. We are lit-  “We’ve always said that Misima needs
       produced in excess of 230,000 ozpa gold   erally following what Placer did; back in   a funding source or a stepping-stone and
       over 15 years before open pit operations   their day silver provided 10% of revenue.   Livingstone could be that,” Corbett said.
       were shuttered in 2004.             Hopefully that will be a similar number for   “If we can drill Livingstone out in the
        So far, Kingston has managed to work   us, our silver is a lower grade but we are   next six months and a get a resource
       up a total inferred and indicated resource   very optimistic we can improve the re-  on that, there’s an opportunity for some
       of 105mt @ 0.93 g/t for 3.21 moz gold   coveries. If we can get the silver recover-  means of cash flow via toll treating or as-
       and 18 moz @ 5.4 g/t silver.        ies up a bit, it might be a 10% by-product   set sale. We’ve always liked having two
        An indicated resource of 49.9mt @   credit which will be very handy,” he said.  projects together and if we can drill Liv-
       0.95 g/t for 1.52 moz gold is the platform   With the Placer template to follow and   ingstone in July and a few months later
       for the Misima PFS. The 220,000oz re-  a tailwind in the gold sector, Corbett said   get back to Misima, that will be ideal.”
       source at Quartz Mountain is primed to   a final investment decision on Misima in
                                                                                              – Mark Andrews































                                                           Misima produced 230,000 ozpa gold for 15 years when owned by Placer