Page 13 - Planet Organic PMO Presentation
P. 13
PMO Fees
We recognize the need for Planet Organic to rapidly develop the PMO in a LEAN, cost efficient manner. The
size of the PMO can be flexed to suit the services.
The team and costs associated with the PMO can viewed in TABLE 1 below. We anticipate resources
fluctuating due to workload so have shown the capacity for Lewis to support on an ad hoc basis. We also
have Maxine available to further support Sundeep.
Days per month
No Position Resource
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Director Matt Buntine
Project
2 Sundeep Dev 6 11 12 12 12 12 12 12 12 12 12
Director
3 LPM/SPM Flexible Resource
4 PM Maxine Williams 4 8 10 10 10 10 10 10 10 10 10
Lewis Walcott (Flexible
5 APM
resource)
6 APM Stephanie Heaney 2 2 2
Rate per £6,589 £13,495 £15,402 £15,402 £14,392 £14,392 £14,392 £14,392 £14,392 £14,392 £14,392
month
TABLE 1: PMO Fees based on a day rate per month