Shell EPCM LITE Delivery Team WHAT’S DIFFERENT:
• Leaner delivery model – Refined DCAF and PEP
processes
• Open to new contractors outside of the existing pool
• Design completed in-house driving specification &
cost improvements
• Access to public sector procurement frameworks
• VI & KPI commitment to the overall team
• Matrix reporting of data to HSSE and commercial
• No additional investment required from Shell.
Existing 2022 hire plan
• Reduced site presence from PM’s due to reduced
work complexity
Programme to setup:
• It would take 3 months to setup from start to fin-
ish.
• If the workload is limited we can be flexible to
expand and retract the team
• DCAF/ PEP revision required during the 3 month
set up period
Key rituals:
PMC – Monthly meetings
Shell – Monday calls