Chapter 9 Sanitation systems

                ●  The condense pipe should be made of a proprietary drainpipe material, such
                   as PVCu, ABS, PP or PVC.
                ●  Metal pipework of any kind is not acceptable due to the acidic nature of the
                   condensate.
                ●  The pipework must be at least 21.5 mm diameter and fully supported with
                   suitably spaced clips to prevent sagging.
                ●  The pipe must be installed to a minimum angle of fall of at least 2.5° or
                   50 mm in every 1 m.
                ●  The length of pipe should not exceed 3 m.
                ●  External runs should be a short as possible, and a minimum of 32 mm
                   diameter waste pipe.
                ●  External pipework must be protected against freezing by insulation of an
                   appropriate thickness along its entire run.
                ●  Connections to rainwater drains are not permitted unless the rainwater drain
                   connects to a foul drain.
                ●  Since most combination boilers contain a 75 mm condensate trap, external
                   traps are not required unless the boiler manufacturer states otherwise.
                   Manufacturers’ data should be checked before the installation of condense
                   pipework. Manufacturers’ data should be checked before the installation of
                   condense pipework.

















                                       Internal
                                       soil pipe



                                                                                                    Pipe must be insulated.
                                                         Condense pipework                          It must terminate above
                                                           Min. 2.5° fall                           the water level but below
               Condense pipework                                                                    the surrounding surface.
                 Min. 2.5º fall                                                                     Pipe end cut to 45°
                               Trap installed
                               if required


               p  Figure 9.92 Termination to a soil stack  p  Figure 9.93 Termination to a drain or gulley