Control of Inspection,

                                       Measuring & Test Equipment


                 a.   PURPOSE
                      The  purpose  of this  procedure  is  to  ensure  that  inspection,  measuring  and  test
                      equipment used by the company is adequately controlled and that appropriate records
                      are maintained so as to meet specified requirements.
                 b.   SCOPE OF APPLICATION

                      The application of this procedure applies to all equipment used to verify, measure or
                      test  product  quality  and  to all  personnel using,handling,storing  or checking  such
                      equipment.

                 c.   DEFINITIONS
                      None.

                 d.   CROSS REFERENCES
                            Quality manual, clause d.11

                            Process control QAP 90
                            Training – QAP 180

                 e.   RESPONSIBILTY FOR APPLICATION
                      The workshop in charge and project engineers are responsible, at varying intervals,
                      for the application of this procedure.

                 f.   PROCESS
                      General

                      The inspection, measuring and test equipment owned by the company for the application
                      detailed in clause 2 above is at present limited to survey instruments such as levels
                      and theodolities.
                      Inspection, measuring and test equipment which is hired for specific application shall
                      be subject to control as dictated by requirement of contract, specification or customer
                      / customers representative. With the exception of clauses f.1, f.3, f.4, f.9 and f.11, all
                      other controls detailed below apply to hired equipment.

                      f.1   A  master  list  of  all inspection,  measuring  and  test  equipment  owned by  the
                            company and used for the application as detailed in clause 2 above shall be
                            maintained by the workshop in charge and any such newly purchased equipment
                            shall have its details added to the master list.  All such equipment should have a
                            means  of  identification  which  is  traceable  back  to  the  master  list.    Such
                            identification should  show, as  a minimum,  the instrument  name or  reference
                            number and the next date for testing / calibration.
                      f.2   When the purchase of new inspection, measuring and test equipment or the hire
                            of special equipment is required, checks shall be made by the workshop in charge
                            (for  new equipment  purchases) or  the relevant  project engineer  (for   hired
                                                                                                            116