have been successfully carried out as required and that relevant records
                                  are available to demonstrate this.

                            f.3.2 Where elements require further attention this shall be recorded in the form
                                  of a snagging list and any necessary action shall be arranged by the Project
                                  Engineer to rectify the situation.  Such elements shall be re inspected.
                                  Records of the snagging inspection and re-inspection shall be maintained
                                  as quality records.

                            f.3.3 Once all the applicable works are satisfactory and acceptable to the Project
                                  Engineer he shall request the customers representative to inspect the work
                                  as required by the contract / specification. Where unsatisfactory works
                                  are identified this shall be recorded and the procedure outlined in clause
                                  6.3.2 above shall be followed.  Again, records of the inspection shall be
                                  maintained as quality records.
                            f.3.4 When  all  works  are  complete  to  the  satisfaction  of  the  customers
                                  representative the Project Engineer should formally request a certificate
                                  of practical completion to be issued from the customers representative. At
                                  such  time  the  contractual  maintenance  period  shall  commence  and
                                  contractual maintenance shall be carried out in accordance with the relevant
                                  process control procedure.
                            f.3.5 At the end  of the  maintenance period, the General Manager Nominee
                                  shall request for final inspection and any elements requiring attention shall
                                  be dealt with in accordance with the relevant sections of clauses f.3.2 and
                                  f.3.2 above. Again, records of the inspection and re-inspection shall be
                                  maintained as quality records.
                            f.3.6 Upon successful completion of all necessary snagging works the General
                                  Manager Nominee  shall formally  hand over  the  works  with no  further
                                  obligation to the contractor and request that the final certificate be issued
                                  as appropriate.

                            f.3.7 Copies  of  snagging  lists  should  be  copied  to  the  management
                                  representative for the purposes of identifying whether any items require
                                  further corrective or preventive action so as to avoid recurrence. Where
                                  such is required it will  be carried out in accordance with customer complaint,
                                  corrective and preventive action procedures.

                 f.  RECORDS
                      All inspection records (including snagging lists and subsequent inspections) shall be
                      maintained in a job file at the main office (GM) for the duration of the contract, including
                      the maintenance period, plus a minimum period of one year.
                      Practical completion and final certificates shall be maintained by the General Manager
                      for the duration of the contract, including the maintenance period, plus a minimum
                      period of one year.
                 g.   FILING

                      The master copy of this procedure is filed by the Management representative together

                      with other procedures under the number QAP 100.
                 h.   ATTACHMENTS

                      Not Applicable