by the company, checking of references, or any other means that facilitate
                                  adequate evaluation, were contractually agreed client/consultant approved
                                  sub- contractor/supplier will be utilized irrespective of whether they are
                                  listed or  not on ASL, as a result no list of sub-contractors will be maintained.
                            f.1.4 The  General Manager may carry out the above evaluations. However,
                                  inclusion  of  new  sub-contractors  /  suppliers  on  to  the ASL  must  be
                                  authorized by the GM following review and grading allocation.
                            f.1.5  The  GM  in  conjunction  with  Purchasing  in  Charge  shall  review  the
                                  performance of approved sub-contractors / suppliers during management’s
                                  review. Such evaluations shall be based on reports of either good or poor
                                  service reports shall be submitted to the Project Engineer at the end of the
                                  project to the Purchasing In-Charge.

                            f.1.6 Sub-contractor / supplier gradings shall be adjusted  as a result of the
                                  above evaluation  in accordance  with clause  f.1.7 below  and  the ASL
                                  amended accordingly. The amended ASL must then be distributed to all
                                  concerned functions for the purposes of inspection control.
                            f.1.7 Following review / appraisal one of the following grades shall be allocated.

                                      Excellent (minimal control / inspection required)
                                      Above average (intermediate control / inspection required)
                                      Average or required standard (normal control / inspection required)
                                      Below average (increased control / inspection required)
                                      Poor (Not to be used without Managing Director’s permission)
                            f.1.8 Based on the review, Purchasing in Charge / GM may contact those sub-
                                  contractors / suppliers whose performance falls below the required standard
                                  and request the implementation of suitable corrective measures. Should
                                  subsequent review of such a sub-contractor / supplier’s performance prove
                                  that  no  improvement  has  been  forthcoming then  that sub-contractor  /
                                  supplier will be graded as “X” on the ASL.

                            f.1.9 “X” graded sub-contractors / suppliers can only be used with the express
                                  written permission of the Managing Director. Upgrading of such on to the
                                  ASL can only be done where there is proof that the required improvements
                                  have been implemented.
                     f.2 PURCHASING DATA

                            f.2.1 Purchase  documents  (including  requisitions)  must obtain  a  clear  and
                                  unambiguous description  of  the  product being  purchased (material  or
                                  service) including any technical data, the quantity required and the required
                                  delivery date (s). When applicable, the purchase document shall include
                                  reference to relevant drawings, specifications, standards, codes and any
                                  other relevant data.
                            f.2.2 The agreed quality assurance requirements and provisions for setting of
                                  quality disputes shall be stipulated in the purchase documents only when
                                  it is felt appropriate or necessary.

                     f.3 VERIFICATION ARRANGEMENTS
                            f.3.1 e the company wishes to verify purchased product at the sub-contractor’s
                                  /  suppliers premises,  the verification  arrangements  and  the method  of
                                  product release shall be specified in the purchasing documents.