QAP 70








                              Control of Customer Supplied Product


                 a.  PURPOSE
                     The purpose of this procedure is to ensure control of products supplied by the customer.

                 b.  SCOPE OF APPLICATION

                     This procedure applies to all customer supplied products.
                 c.  DEFINITIONS

                     Customer Supplied Product: Means; any material, component or equipment supplied
                      by the customer for incorporation into the final product.

                 d.  CROSS REFERENCES
                            Quality Maunal, Clause d.7

                            Contact Review – QAP 30
                            Inspection and Testing – QAP 100

                            Control of Non-conforming Product – QAP 130
                 e.  RESPONSIBILITY FOR APPLICATION

                     The Chief Estimator and Project Engineer are jointly responsible, at varying intervals,
                      for  the application of this procedure.
                 f.  PROCESS

                      f.1  Verification of Customer Supplied Products
                           f.1.1 Customer supplied product may include materials / equipment that can be
                                  installed during the construction stages of the project.
                           f.1.2 Where the Chief Estimator identifies such customer supplied products
                                  during contract review details shall be  passed to the Project Engineer
                                  who must then liaise with the customer to ensure that products will be
                                  available on time as not delay completion / delivery dates. Where delay is
                                  likely the customer or his representative should be informed in writing.

                           f.1.3 Products supplied by the customer shall be inspected on receipt by the
                                  Project  Engineers  or  his  delegated  representative  I accordance  with
                                  Inspection and testing procedures.
                           f.1.4 Should products provided by the customer be found unsuitable for use
                                  (e.g. not of correct specification, damaged in transit, of insufficient quantity,
                                  etc.) details will be recorded by the Inspector and be notified in writing by
                                  the  Project  Engineer  who  shall  also  request  from  the  customer
                                  arrangements or instruction for replacement.

                           f.1.5 All replacements will be inspected as per original requirements.